Practice Standard for Earned Value Management
Inhalt der Mindmap
Practice Standard for Earned Value Management
EVM performance analysis and forecasting
- Schedule analysis and forecasting
- schedule variance
- when is a positive value indicates a favorable condition
- when is a negative value indicates a unfavorable condition
- sv=ev-pv
- this is a percentage sv%= sv=pv
- schedule performance index
- indicates how efficiently the project team is using it is time
- SPI =ev/pv
- time estimate at completion
- estimate of when the project will be completed, if current trends continue
- EAC=(BAC/SPI)/ (BAC/months)
- schedule variance
- cost analysis and forecasting
- to-complete performance index
- TCPI=(BAC_EV)/(BAC_AC)
- cost performance index
- CPI=EV/AC
- is the cumulative cost efficiency of a project
- CPI=EV/AC
- cost variance
- CV=EV_AC
- shows whether a project is under or over budget
- CV=EV_AC
- estimate at completion
- EAC=AC+ETC
- ETC=(BAC_EV)/CPI
- EAC=AC+[(BAC-EV)/CPI]= BAC/CPI
- equivalent
- variance at completion
- VAC=BAC_EAC
- VAC%= VAC/BAC
- estimate at completion
- EAC=BAC/CPI
- to-complete performance index
- management by exception
- this practice contributes greatly to the efficiency and effectiveness of project management
- Schedule analysis and forecasting
Guidance for the use of key EVM practices
- establish a performance measurement baseline
- develop time-phased budget for each work task
- the full scope of work each task or activity must be schedule and resourced
- assign unambiguous management responsability
- integrated management of work scope, schedule, and cost requires that a single individual.
- decompose work scope to a manageable level
- most work scopes broken down for optimal planning, execution, and control.
- select earned value measurement techniques for all tasks
- en EV techniques is selected for each task based on the temporal and physical qualities of the work
- maintain integrity of performance measurement baseline throughout the project
- the four key practices established, relating scope, schedule and cost.
- develop time-phased budget for each work task
- Measure and Analyze performance against the baseline
- record resource usage during project execution
- in EVM, the cost associated with the performance of work scope must be recorded on a regular basis.
- objectively measure the physical work progress
- many research projects, however, yield only intangible outcomes until their final product emerges at the end.
- credit earned value according to earned value techniques
- also assures thet earned values are credited in the same measurement unit used to establish planned values and record actual cost.
- analyze and forecast cost/Schedule performance
- The funtion of EVM forecat is to compare their objetive values with management estimates offered by project delivery team members
- report performance problems and/or take action
- it is critical that EVM provide the best possible feedback to those who must make the decisions and take the actions.
- record resource usage during project execution
- establish a performance measurement baseline
Informationen
- Beschreibung
- Ingeniería Mindmap am Practice Standard for Earned Value Management, erstellt von camila moreno aldana am 06/11/2017.
- Erstellt von
- camila moreno aldana · Nov 2017
- Aktualisiert
- 6 Nov 2017
- Aufrufe
- 0
- Verlauf
-
- Erstellt von camila moreno aldana · 6 Nov 2017
- Kopiert von camila moreno aldana · 6 Nov 2017
- Bewertung