Practice Standard for Work Breakdown Structures

jonathan villalba huaman Spanisch

Practice Standard for Work Breakdown Structures

Inhalt der Mindmap

Practice Standard for Work Breakdown Structures

  1. 1) Introduction to the Practice Standard for Work Breakdown Structures

    • Overview
      • Successful project management relies on thorough planning.
      • This begins by defining the project objectives with sufficiently detailed information
    • Concepts
      • The WBS define the project’s life cycle as well as the deliverables appropriate to the project, program, or portfolio.
      • A key input to other project management processes and deliverables.
    • Objectives
      • Provides a common ground for understanding the concepts and benefits of the WBS
      • Present a standard application of the WBS as a project management tool.
  2. 2) Defining the WBS

    • Overview
      • The WBS represents a clear description of the project’s deliverables and scope.
      • The WBS subdivides the project work into smaller, more manageable pieces of work.
    • Common Usage of Terms
      • Work
        • Sustained physical or mental effort
      • Breakdown
        • Division into parts or categories; separation into simpler substances; decomposition.
      • Structure
        • Something arranged in a definite pattern of organization.
      • Deliverable
      • Oriented
        • Focused toward the concerns and interests of a specific group
      • Hierarchical
        • Classified according to various criteria into successive levels or layers.
      • Decomposition
      • Definition of Terms
        • Activity
        • Apportioned Effort
        • Control Account
        • Discrete Effort.
        • Level of Effort
        • Task
        • Work Breakdown Structure Component.
        • Work Package
        • WBS Element.
    • Concepts
      • Overview
        • The WBS provides a clear vision of the work of the project.
      • Deliverables
        • Any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project.
      • Deign
        • It provides a graphical representation or textual outline of the project scope
      • Management
        • Providing a framework for specifying performance objectives
        • Supporting the planning and assignment of responsibilities
      • The 100% Rule
        • The sum of the work at the ‘‘child’’ level must equal 100% of the work represented by the ‘‘parent’’
  3. 3) Importance of the WBS

    • Overview
      • The WBS provides the baseline for subsequent change control
      • Project failures, however, can often be traced back to a poorly developed or nonexistent WBS.
    • Relationship to Other Tools
      • There are many project management tools that use the WBS as input :
        • Project Charter
        • Project Scope Statement.
        • Program and Portfolio WBS
        • RBS
        • OBS
        • WBS Dictionary:
        • Project Schedule Network Diagram
        • Project Schedule
  4. 4) Defining WBS Quality

    • Overview
      • To state that a particular WBS is of high quality, one must agree that the WBS has been created so that it satisfies the purpose for which it was created
    • WBS Quality Principle 1
      • Sub-Principle 1—Core Characteristics
        • These characteristics represent the minimum set of specific attributes a WBS must contain
      • Sub-Principle 2—Use-Related Characteristics
        • These characteristics enable the WBS to be used for purposes that are unique to a specific project, industry or environment
    • WBS Quality Principle 2
      • There is no conceptual difference between a project WBS, a program WBS, and a portfolio WBS.
    • Problem Diagnostic Checklist
      • The project scope has changed and is unmanageable
        • Has a WBS been created for the project?
      • Individuals are unable to use the new product or feature
        • Are the WBS elements deliverable-focused?

Bilder und Dateien der Mindmap

  • Practice Standard for Work Breakdown Structures

Informationen

Beschreibung
Mindmap am Practice Standard for Work Breakdown Structures, erstellt von jonathan villalba huaman am 15/04/2018.
Aufrufe
0
Bewertung

Mehr zu Project Scope Management