6. PROJECT SCHEDULE MANAGEMENT
Inhalt der Mindmap
6. PROJECT SCHEDULE MANAGEMENT
6.1 Plan Schedule Management
- It establishes the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
- .1 Inputs
- .1 Project charter
- Defines the summary milestone schedule that will influence the management of the project schedule
- .2 Project management plan
- .3 Enterprise environmental factors
- .4 Organizational process assets
- .1 Project charter
- .2 Tools & Techniques
- .1 Expert judgment
- .2 Data analysis
- .3 Meetings
- .3 Outputs
- .1 Schedule management plan
- Establishes the criteria and the activities for developing, monitoring, and controlling the schedule
- Project schedule model development
- Used in the development of the project schedule model are specified.
- Release and iteration length
- Level of accuracy
- Specifies the acceptable range used in determining realistic activity duration estimates
- Units of measure.
- Such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers, or cubic yards for quantity measures) is defined for each of the resources
- Organizational procedures links
- Allowing for consistency with the estimates and resulting schedules.
- Project schedule model maintenance
- Used to update the status and record progress of the project in the schedule model
- Control thresholds.
- Variance thresholds for monitoring schedule performance
- Rules of performance measurement.
- EVM Techniques
- Reporting formats.
- .1 Schedule management plan
6.2 Define Activities
- Identify and document the specific actions to be performed to produce the project deliverables.
- .1 Inputs
- .1 Project management plan
- Schedule management plan
- Defines the schedule methodology, the duration o, nd the level of detail necessary to manage the work.
- Scope baseline
- Includes WBS, deliverables, constraints, and assumptions documented
- Schedule management plan
- .2 Enterprise environmental factors
- .3 Organizational process assets
- .1 Project management plan
- It decomposes work packages into schedule activities
- .2 Tools & Techniques
- .1 Expert judgment
- .2 Decomposition
- Used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts
- .3 Rolling wave planning
- Is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level
- .4 Meetings
- May be face-to-face, virtual, formal, or informal
- .3 Outputs
- .1 Activity list
- Includes the schedule activities required on the project
- .2 Activity attributes
- Extend the description of the activity by identifying multiple components associated with each activity
- .3 Milestone list
- Is a significant point or event in a project, have zero duration.
- .4 Change requests
- .5 Project management plan updates
- Schedule baseline
- Cost baseline
- .1 Activity list
6.3 Sequence Activities
- Identifying and documenting relationships among the project activities
- .1 Inputs
- .1 Project management plan
- • Schedule management plan • Scope baseline
- .2 Project documents
- • Activity attributes • Activity list • Assumption log • Milestone list
- .3 Enterprise environmental factors
- .4 Organizational process assets
- .1 Project management plan
- .2 Tools & Techniques
- .1 Precedence diagramming method (PDM)
- Finish-to-start (FS).
- Is the most commonly used type of precedence relationship
- Finish-to-finish (FF).
- a successor activity cannot finish until a predecessor activity has finished
- Start-to-start (SS).
- a successor activity cannot start until a predecessor activity has started.
- Start-to-finish (SF).
- Is very rarely used
- Finish-to-start (FS).
- .2 Dependency determination and integration
- Mandatory dependencies
- Are legally or contractually required or inherent in the nature of the work.
- Discretionary dependencies
- Both activities may occur at the same time (in parallel)
- External dependencies.
- Involve a relationship between project activities and non project activities, are usually outside of the project team’s control
- Internal dependencies
- Involve a precedence relationship between project activities and are generally inside the project team’s control.
- Mandatory dependencies
- .3 Leads and lags
- Leads: Is the amount of time a successor activity can be advanced with respect to a predecessor activity.
- Lags: Is the amount of time a successor activity will be delayed with respect to a predecessor activity
- .4 Project management information system (PMIS)
- To help plan, organize, and adjust the sequence of the activities; insert the logical relationships, lead and lag values; and differentiate the different types of dependencies.
- .1 Precedence diagramming method (PDM)
- .3 Outputs
- .1 Project schedule network diagrams
- Is a graphical representation of the logical relationships
- Activities that have multiple predecessor activities indicate a path convergence
- Activities that have multiple successor activities indicate a path divergence.
- .2 Project documents updates
- • Activity attributes • Activity list • Assumption log • Milestone list
- .1 Project schedule network diagrams
- it is defines the logical sequence of work
6.4 Estimate Activity Durations
- Estimating the number of work periods needed to complete individual activities with the estimated resources.
- Provides the amount of time each activity will take to complete.
- .1 Inputs
- .1 Project management plan
- • Schedule management plan • Scope baseline
- .2 Project documents
- • Activity attributes • Activity list • Assumption log • Lessons learned register • Milestone list • Project team assignments • Resource breakdown structure • Resource calendars • Resource requirements • Risk register
- .3 Enterprise environmental factors
- .4 Organizational process assets
- .1 Project management plan
- .2 Tools & Techniques
- .1 Expert judgment
- .2 Analogous estimating
- Is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. It is also less accurate
- .3 Parametric estimating tE = (tO + tM + tP) / 3.
- Uses a statistical relationship between historical data and other variables to calculate cost,budget, and duration.
- .4 Three-point estimating
- Most likely (tM).
- Is based on the duration of the activity
- Optimistic (tO).
- Activity duration based on analysis of the best-case scenario for the activity
- Pessimistic (tP).
- Duration based on analysis of the worst-case scenario for the activity
- Most likely (tM).
- .5 Bottom-up estimating
- Is a method of estimating project duration or cost by aggregating the estimates of the lower level components of the WBS.
- .6 Data analysis
- • Alternatives analysis
- Used to compare various levels of resource capability or skills; scheduling compression techniques, different tools ; and make, rent, or buy decisions regarding the resources
- • Reserve analysis
- Used to determine the amount of contingency and management reserve needed for the project.
- • Alternatives analysis
- .7 Decision making
- .8 Meetings
- 3.Outputs
- .1 Duration estimates
- Are quantitative assessments of the likely number of time periods that are required to complete an activity, a phase, or a project
- .2 Basis of estimates
- .3 Project documents updates
- •Activity attributes • Assumption log • Lessons learned register
- .1 Duration estimates
6.5 Develop Schedule
- Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
- Generates a schedule model with planned dates for completing project activities
- .1 Inputs
- .1 Project management plan
- .2 Project documents
- Basis of estimates, Duration estimates, Project schedule network diagrams
- .3 Agreements
- .4 Enterprise environmental factors
- .5 Organizational process assets
- .2 Tools & Techniques
- .1 Schedule network analysis
- Used to generate the project schedule model
- Is an iterative process that is employed until a viable schedule model is developed.
- .2 Critical path method
- Used to estimate the minimum project duration and
- .3 Resource optimization
- Used to adjust the start and finish dates of activities
- .4 Data analysis
- • What-if scenario analysis
- Process of evaluating scenarios in order to predict their effect, positive or negative, on project objectives
- • Simulation
- Involves calculating multiple work package durations with different sets of activity assumptions, constraints, risks, issues, or scenarios using probability distributions . Monte Carlo analysis is most famous example.
- • What-if scenario analysis
- .5 Leads and lags
- Leads: are used in limited circumstances to advance a successor activity with respect to the predecessor activity
- Lags: are used in limited circumstances where processes require a set period of time to elapse between the predecessors and successors without work or resource impact.
- .6 Schedule compression
- Used to shorten or accelerate the schedule duration
- Crashing
- Used to shorten the schedule duration for the least incremental cost by adding resources
- Fast tracking
- The activities or phases are performed in parallel for at least a portion of their duration.
- .7 Project management information system( PMIS)
- .8 Agile release planning
- Provides a high-level summary timeline of the release schedule
- .1 Schedule network analysis
- .3 Outputs
- .1 Schedule baseline
- Is the approved version of a schedule model, is used as a basis for comparison to actual results, is a component of the project management plan.
- .2 Project schedule
- Is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources
- Bar/Gant charts
- Milestone charts.
- Identify the scheduled start or completion of major deliverables and key external interfaces.
- Project schedule network diagrams
- Presented in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic diagram
- Is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources
- .3 Schedule data
- Is the collection of information for describing and controlling the schedule.
- .4 Project calendars
- Identifies working days and shifts that are available for scheduled activities
- .5 Change requests
- .6 Project management plan updates
- • Schedule management plan
- • Cost baseline
- .7 Project documents updates
- • Activity attributes • Assumption log • Duration estimates • Lessons learned register • Resource requirements • Risk register
- .1 Schedule baseline
6.6 Control Schedule
- Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
- .1 Inputs
- .1 Project management plan
- • Schedule management plan • Schedule baseline • Scope baseline • Performance measurement baseline
- .2 Project documents
- • Lessons learned register • Project calendars • Project schedule • Resource calendars • Schedule data
- .3 Work performance data
- Contains data on project status
- .4 Organizational process assets
- .1 Project management plan
- .2 Tools & Techniques
- .1 Data analysis
- • Earned value analysis
- Earned value analysis
- The (SV) and (SPI) are used to assess the magnitud of variation to the original schedule baseline.
- Iteration burndown chart
- Is used to analyze the variance with respect to an ideal burndown based on the work committed from iteration planning
- Performance reviews
- compare, and analyze schedule performance against the schedule baseline
- Trend analysis
- Examines project performance over time to determine whether performance is improving or deteriorating
- Variance analysis
- Examine the t variances in planned versus actual start and finish dates, planned versus actual durations, and variances in float
- What-if scenario analysis
- Is used to assess the various scenarios guided by the output from the Project Risk Management processes
- Earned value analysis
- • Earned value analysis
- .2 Critical path method
- Can help determine schedule status
- .3 Project management information system (PMIS)
- .4 Resource optimization
- Involve the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time.
- .5 Leads and lags
- .6 Schedule compression
- .1 Data analysis
- .3 Outputs
- .1 Work performance information
- Includes information on how the project work is performing compared to the schedule baseline.
- For projects using earned value analysis, the (SV) and (SPI) are documented for inclusion in work performance reports
- .2 Schedule forecasts
- Schedule updates are forecasts of estimates or predictions of conditions and events in the project’s future based
- .3 Change requests
- .4 Project management plan updates
- • Schedule management plan
- May be updated to reflect a change in the way the schedule is managed.
- • Schedule baseline
- May be updated to reflect changes caused by schedule compression techniques or performance issues.
- • Cost baseline
- Are incorporated in response to approved changes in scope, resources, or cost estimates.
- • Performance measurement baseline
- Are incorporated in response to approved changes in scope, schedule performance, or cost estimates.
- • Schedule management plan
- .5 Project documents updates
- • Assumption log
- • Basis of estimates
- • Lessons learned register
- • Project schedule
- • Resource calendars
- • Risk register
- • Schedule data
- .1 Work performance information
- Benefit: The schedule baseline is maintained throughout the project