6. PROJECT SCHEDULE MANAGEMENT

MARILUZ TAYPE ALMONACID Spanisch

Inhalt der Mindmap

6. PROJECT SCHEDULE MANAGEMENT

  1. 6.1 Plan Schedule Management

    • It establishes the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
    • .1 Inputs
      • .1 Project charter
        • Defines the summary milestone schedule that will influence the management of the project schedule
      • .2 Project management plan
      • .3 Enterprise environmental factors
      • .4 Organizational process assets
    • .2 Tools & Techniques
      • .1 Expert judgment
      • .2 Data analysis
      • .3 Meetings
    • .3 Outputs
      • .1 Schedule management plan
        • Establishes the criteria and the activities for developing, monitoring, and controlling the schedule
        • Project schedule model development
          • Used in the development of the project schedule model are specified.
        • Release and iteration length
        • Level of accuracy
          • Specifies the acceptable range used in determining realistic activity duration estimates
        • Units of measure.
          • Such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers, or cubic yards for quantity measures) is defined for each of the resources
        • Organizational procedures links
          • Allowing for consistency with the estimates and resulting schedules.
        • Project schedule model maintenance
          • Used to update the status and record progress of the project in the schedule model
        • Control thresholds.
          • Variance thresholds for monitoring schedule performance
        • Rules of performance measurement.
          • EVM Techniques
        • Reporting formats.
  2. 6.2 Define Activities

    • Identify and document the specific actions to be performed to produce the project deliverables.
    • .1 Inputs
      • .1 Project management plan
        • Schedule management plan
          • Defines the schedule methodology, the duration o, nd the level of detail necessary to manage the work.
        • Scope baseline
          • Includes WBS, deliverables, constraints, and assumptions documented
      • .2 Enterprise environmental factors
      • .3 Organizational process assets
    • It decomposes work packages into schedule activities
    • .2 Tools & Techniques
      • .1 Expert judgment
      • .2 Decomposition
        • Used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts
      • .3 Rolling wave planning
        • Is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level
      • .4 Meetings
        • May be face-to-face, virtual, formal, or informal
    • .3 Outputs
      • .1 Activity list
        • Includes the schedule activities required on the project
      • .2 Activity attributes
        • Extend the description of the activity by identifying multiple components associated with each activity
      • .3 Milestone list
        • Is a significant point or event in a project, have zero duration.
      • .4 Change requests
      • .5 Project management plan updates
        • Schedule baseline
        • Cost baseline
  3. 6.3 Sequence Activities

    • Identifying and documenting relationships among the project activities
    • .1 Inputs
      • .1 Project management plan
        • • Schedule management plan • Scope baseline
      • .2 Project documents
        • • Activity attributes • Activity list • Assumption log • Milestone list
      • .3 Enterprise environmental factors
      • .4 Organizational process assets
    • .2 Tools & Techniques
      • .1 Precedence diagramming method (PDM)
        • Finish-to-start (FS).
          • Is the most commonly used type of precedence relationship
        • Finish-to-finish (FF).
          • a successor activity cannot finish until a predecessor activity has finished
        • Start-to-start (SS).
          • a successor activity cannot start until a predecessor activity has started.
        • Start-to-finish (SF).
          • Is very rarely used
      • .2 Dependency determination and integration
        • Mandatory dependencies
          • Are legally or contractually required or inherent in the nature of the work.
        • Discretionary dependencies
          • Both activities may occur at the same time (in parallel)
        • External dependencies.
          • Involve a relationship between project activities and non project activities, are usually outside of the project team’s control
        • Internal dependencies
          • Involve a precedence relationship between project activities and are generally inside the project team’s control.
      • .3 Leads and lags
        • Leads: Is the amount of time a successor activity can be advanced with respect to a predecessor activity.
        • Lags: Is the amount of time a successor activity will be delayed with respect to a predecessor activity
      • .4 Project management information system (PMIS)
        • To help plan, organize, and adjust the sequence of the activities; insert the logical relationships, lead and lag values; and differentiate the different types of dependencies.
    • .3 Outputs
      • .1 Project schedule network diagrams
        • Is a graphical representation of the logical relationships
        • Activities that have multiple predecessor activities indicate a path convergence
        • Activities that have multiple successor activities indicate a path divergence.
      • .2 Project documents updates
        • • Activity attributes • Activity list • Assumption log • Milestone list
    • it is defines the logical sequence of work
  4. 6.4 Estimate Activity Durations

    • Estimating the number of work periods needed to complete individual activities with the estimated resources.
    • Provides the amount of time each activity will take to complete.
    • .1 Inputs
      • .1 Project management plan
        • • Schedule management plan • Scope baseline
      • .2 Project documents
        • • Activity attributes • Activity list • Assumption log • Lessons learned register • Milestone list • Project team assignments • Resource breakdown structure • Resource calendars • Resource requirements • Risk register
      • .3 Enterprise environmental factors
      • .4 Organizational process assets
    • .2 Tools & Techniques
      • .1 Expert judgment
      • .2 Analogous estimating
        • Is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. It is also less accurate
      • .3 Parametric estimating tE = (tO + tM + tP) / 3.
        • Uses a statistical relationship between historical data and other variables to calculate cost,budget, and duration.
      • .4 Three-point estimating
        • Most likely (tM).
          • Is based on the duration of the activity
        • Optimistic (tO).
          • Activity duration based on analysis of the best-case scenario for the activity
        • Pessimistic (tP).
          • Duration based on analysis of the worst-case scenario for the activity
      • .5 Bottom-up estimating
        • Is a method of estimating project duration or cost by aggregating the estimates of the lower level components of the WBS.
      • .6 Data analysis
        • • Alternatives analysis
          • Used to compare various levels of resource capability or skills; scheduling compression techniques, different tools ; and make, rent, or buy decisions regarding the resources
        • • Reserve analysis
          • Used to determine the amount of contingency and management reserve needed for the project.
      • .7 Decision making
      • .8 Meetings
    • 3.Outputs
      • .1 Duration estimates
        • Are quantitative assessments of the likely number of time periods that are required to complete an activity, a phase, or a project
      • .2 Basis of estimates
      • .3 Project documents updates
        • •Activity attributes • Assumption log • Lessons learned register
  5. 6.5 Develop Schedule

    • Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
    • Generates a schedule model with planned dates for completing project activities
    • .1 Inputs
      • .1 Project management plan
      • .2 Project documents
        • Basis of estimates, Duration estimates, Project schedule network diagrams
      • .3 Agreements
      • .4 Enterprise environmental factors
      • .5 Organizational process assets
    • .2 Tools & Techniques
      • .1 Schedule network analysis
        • Used to generate the project schedule model
        • Is an iterative process that is employed until a viable schedule model is developed.
      • .2 Critical path method
        • Used to estimate the minimum project duration and
      • .3 Resource optimization
        • Used to adjust the start and finish dates of activities
      • .4 Data analysis
        • • What-if scenario analysis
          • Process of evaluating scenarios in order to predict their effect, positive or negative, on project objectives
        • • Simulation
          • Involves calculating multiple work package durations with different sets of activity assumptions, constraints, risks, issues, or scenarios using probability distributions . Monte Carlo analysis is most famous example.
      • .5 Leads and lags
        • Leads: are used in limited circumstances to advance a successor activity with respect to the predecessor activity
        • Lags: are used in limited circumstances where processes require a set period of time to elapse between the predecessors and successors without work or resource impact.
      • .6 Schedule compression
        • Used to shorten or accelerate the schedule duration
        • Crashing
          • Used to shorten the schedule duration for the least incremental cost by adding resources
        • Fast tracking
          • The activities or phases are performed in parallel for at least a portion of their duration.
      • .7 Project management information system( PMIS)
      • .8 Agile release planning
        • Provides a high-level summary timeline of the release schedule
    • .3 Outputs
      • .1 Schedule baseline
        • Is the approved version of a schedule model, is used as a basis for comparison to actual results, is a component of the project management plan.
      • .2 Project schedule
        • Is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources
          • Bar/Gant charts
          • Milestone charts.
            • Identify the scheduled start or completion of major deliverables and key external interfaces.
          • Project schedule network diagrams
            • Presented in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic diagram
      • .3 Schedule data
        • Is the collection of information for describing and controlling the schedule.
      • .4 Project calendars
        • Identifies working days and shifts that are available for scheduled activities
      • .5 Change requests
      • .6 Project management plan updates
        • • Schedule management plan
        • • Cost baseline
      • .7 Project documents updates
        • • Activity attributes • Assumption log • Duration estimates • Lessons learned register • Resource requirements • Risk register
  6. 6.6 Control Schedule

    • Analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.
    • .1 Inputs
      • .1 Project management plan
        • • Schedule management plan • Schedule baseline • Scope baseline • Performance measurement baseline
      • .2 Project documents
        • • Lessons learned register • Project calendars • Project schedule • Resource calendars • Schedule data
      • .3 Work performance data
        • Contains data on project status
      • .4 Organizational process assets
    • .2 Tools & Techniques
      • .1 Data analysis
        • • Earned value analysis
          • Earned value analysis
            • The (SV) and (SPI) are used to assess the magnitud of variation to the original schedule baseline.
          • Iteration burndown chart
            • Is used to analyze the variance with respect to an ideal burndown based on the work committed from iteration planning
          • Performance reviews
            • compare, and analyze schedule performance against the schedule baseline
          • Trend analysis
            • Examines project performance over time to determine whether performance is improving or deteriorating
          • Variance analysis
            • Examine the t variances in planned versus actual start and finish dates, planned versus actual durations, and variances in float
          • What-if scenario analysis
            • Is used to assess the various scenarios guided by the output from the Project Risk Management processes
      • .2 Critical path method
        • Can help determine schedule status
      • .3 Project management information system (PMIS)
      • .4 Resource optimization
        • Involve the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time.
      • .5 Leads and lags
      • .6 Schedule compression
    • .3 Outputs
      • .1 Work performance information
        • Includes information on how the project work is performing compared to the schedule baseline.
        • For projects using earned value analysis, the (SV) and (SPI) are documented for inclusion in work performance reports
      • .2 Schedule forecasts
        • Schedule updates are forecasts of estimates or predictions of conditions and events in the project’s future based
      • .3 Change requests
      • .4 Project management plan updates
        • • Schedule management plan
          • May be updated to reflect a change in the way the schedule is managed.
        • • Schedule baseline
          • May be updated to reflect changes caused by schedule compression techniques or performance issues.
        • • Cost baseline
          • Are incorporated in response to approved changes in scope, resources, or cost estimates.
        • • Performance measurement baseline
          • Are incorporated in response to approved changes in scope, schedule performance, or cost estimates.
      • .5 Project documents updates
        • • Assumption log
        • • Basis of estimates
        • • Lessons learned register
        • • Project schedule
        • • Resource calendars
        • • Risk register
        • • Schedule data
    • Benefit: The schedule baseline is maintained throughout the project

Informationen

Beschreibung
Mindmap am 6. PROJECT SCHEDULE MANAGEMENT, erstellt von MARILUZ TAYPE ALMONACID am 22/04/2018.
Aufrufe
1
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck