Chapter 10: Critical Path Method
Inhalt der Mindmap
Chapter 10: Critical Path Method
9. Forward Pass
- process of calculating the early start date (ES) and early finish date (EF) for all the activities
- ES
- earliest date by which an activity can start assuming all the preceding activities are completed as planned
- EF
- earliest date by which an activity can be completed assuming all the preceding activities are completed as planned
- For complete calculation process check book
- ES
- process of calculating the early start date (ES) and early finish date (EF) for all the activities
1. Network Diagram
- graphical presentation of the activities showing the planned sequence of work
- formed by
- list of activities
- logic constraints
- also called precedence diagram method (PDM)
2. Definition of an Activity
- step in which each activity is given a description for the work content understanding of the team members. expanded later into a Job card.
3. Logical Reltionship
- logical elationshipa between activities can be
- Mandatory
- limitations ofthe build method, the MUST be done a certain way
- Discrtionary
- defined by the body of knowledge
- Mandatory
- Activities in
- Series
- performed at the same time, which is a more efficient use oftime than activities in series
- Paralel
- carried out one after the other
- Series
- logical elationshipa between activities can be
4. How to draw Logical Relationships
- logical relationship, constraint, dependency and link are all used interchangeably to represent the lines drawn between the activity boxes
- logical relationship, constraint, dependency and link are all used interchangeably to represent the lines drawn between the activity boxes
5. Activity Logic Table
- logic information is often compiled in a tabular format, with each record (or line) defining a relationship.
- colums: before act., constraints, next act., and or duration
- logic information is often compiled in a tabular format, with each record (or line) defining a relationship.
6. Activity Duration
- info needed
- Activity duration Activity calendar or work pattern
- An activity's duration will run from the start to the finish ofthe activity.
- info needed
7. Calendar and work Pattern
- activity's working profile, in other words, on what days ofthe week the resources or activity will be working
8. Critical Path Method Steps
- Steps
- Draw the logic network diagram
- Assign durations to all the activities
- Impose a work calendar.
- Steps
10. Backward Pass
- Process of calculating the late start date (LS) and late finish date (LF) of each activity
- LS
- The latest date an activity can start to meet the planned completion date.
- LF
- The latest date an activity can finish to meet the planned completion date.
- LS
- For complete calculation process check book
- Process of calculating the late start date (LS) and late finish date (LF) of each activity
11. Activity Float
- is a measure of flexibility, or inherent surplus time in an activity's scheduling.
- This indicates how many working days the activity can be delayed or extended before it will extend the completion date of the project or any target finish dates (milestones).
- is a measure of flexibility, or inherent surplus time in an activity's scheduling.
12. Network Diagram
- Constraints between activities
- Finish-to-Start (FS)
- Represents the relationship linking the finish of an activity with the start of another activity.
- Start-to-Start (SS)
- represents the relationship between the start dates ofthe two activities.
- Finish-to-Finish (FF)
- represents the relationship between the finish oftwo activities.
- Start-to-Finish (SF)
- Represents the relationship linking the start of an activity with the finish of another activity.
- Finish-to-Start (FS)
- Constraints between activities
15. Calendar / Work Pattern
- number of calendars can be defined.
- Rest days are the days of the week that are always taken off
- Holidays can be defined as public holidays, works holidays, or your own personal holidays.
- Activities and resources can be linked to a calendar number.
- defines the days on which work can be scheduled.
- assigned to any of the trades or even one person if appropriate.
- unique combination of rest days and holidays.
14. Definition of an Activity
- unique activity code or number
- An activity may need resources
- activities can be linked to the work packages
- activities will have a calendar or work pattern
- An activity must have a description.
- logical relationships between the activities
- will incur expenses
- activity numbers from the various projects need to be different, when multi project
- As time and resources are linked to the activities they can be integrated to generate a manpower S curve against time for planning and control purposes
- The activity can have target start and finish dates assigned
- An activity may need items to be procured
13. Logical Errors
- Basic logical errors
- Logical loop
- represents an impossible situation
- Logical dangle
- where the activity either comes from nowhere or goes to nowhere
- Redundant precedence relationship
- it is only necessary to indicate an activity's immediate predecessors, not the one before their predecesor
- Logical loop
- Basic logical errors
Bilder und Dateien der Mindmap
Informationen
- Beschreibung
- Mindmap am Chapter 10: Critical Path Method, erstellt von Mariana Alejandra Ruano Rochin am 14/06/2019.
- Erstellt von
- Mariana Alejandra Ruano Rochin
- Aufrufe
- 0
- Bewertung