Mind map: changeover methods
Inhalt der Mindmap
5d - Changeover methods
Parallel
- The old system continues to run while the new system is installed
- When theere is confidence in the new system, the old system is retired
- Advantages
- Accuracy of new system can be compared with legacy system
- Suitable for life/mission crtical systems
- Can revert to old system if there is a problem
- Disadvantages
- All work is duplicated
- May not have spacce for 2 sets of physical equipment
- May result in data integrity issues
Phased
- Parts of a system are introduced one at a time
- Can be combined with all other methods
- Advantages
- Training can be staggered
- Low risk as only part of the system may fail
- Errors can be corrected with little effect on the rest of the system
- Disadvantages
- Old and new systems may not be compatible
- Can take a long time to implement
- Can be confusing 2 different systems at the same time
Pilot
- The system is trialled with a group or department
- Can be combined with all other methods
- Advantages
- Training can be cascaded
- Errors can be corrected before main group go live date
- Low risk as only small group are affected by failure
- Disadvantages
- Can take a long time to implement
- Staff may feel like 'guinea pigs'
- Old and new system may not be compatible
Direct
- The new system takes over from the old system immediately
- The old system is retired immediately
- Advantages
- Can be implemented during non-busy times
- Cheap to implement as no duplication of work
- No risk of data integrity due to duplication
- Disadvantage
- Problems could lead to system failure
- All training must be completed in advance
- Nothing to fall back on