SAB5#48_Validate_Scope

Inhalt der Mindmap
SAB5#48_Validate_Scope
Validate Scope is done to help / ensure the project is on track from the CUSTOMER's / STAKEHOLDER's point of view during the project. It is better to find changes and issues during the project than at the end. The customer will either accept deliverables or make change requests
Work Performance Information
Verified Deliverables
- Work must be completed and checked each time before you meet with the customer
Scope Baseline
- From the Project Management Plan
- It's helpful to have the approved scope with you when you meet with the customer
Requirements Traceability Matrix
- So you can track where requirements came from and prove that requirements were achieved
Inspection
Group Decision-Making Techniques
Accepted Deliverables
- This deliverables are an input for the Close Project / Phase
Requirements Documentation
- To refresh your memory about the full details of the requirements
Change Requests
Project Documents Update
Scope Management Plan
- From the Project Management Plan
- Shows the previously agreed-upon deliverables and plans for gaining formal acceptance for them
Work Performance Data
- From the Direct and Manage Work Control Process
- To assess how well product deliverables are meeting the requirements
Bilder und Dateien der Mindmap
Informationen
- Beschreibung
- Mindmap am SAB5#48_Validate_Scope, erstellt von Israel Miranda Torres am 11/04/2015.
- Erstellt von
- Israel Miranda Torres
- Aufrufe
- 2
- Verlauf
-
- Erstellt von Norberto C · 11 Apr 2015
- Kopiert von Norberto C · 11 Apr 2015
- Kopiert von Israel Miranda Torres · 11 Apr 2015
- Bewertung