  1. Validate Scope is done to help / ensure the project is on track from the CUSTOMER's / STAKEHOLDER's point of view during the project. It is better to find changes and issues during the project than at the end. The customer will either accept deliverables or make change requests

  2. Work Performance Information

  3. Verified Deliverables

    • Work must be completed and checked each time before you meet with the customer
  4. Scope Baseline

    • From the Project Management Plan
    • It's helpful to have the approved scope with you when you meet with the customer
  5. Requirements Traceability Matrix

    • So you can track where requirements came from and prove that requirements were achieved
  6. Inspection

  7. Group Decision-Making Techniques

  8. Accepted Deliverables

    • This deliverables are an input for the Close Project / Phase
  9. Requirements Documentation

    • To refresh your memory about the full details of the requirements
  10. Change Requests

  11. Project Documents Update

  12. Scope Management Plan

    • From the Project Management Plan
    • Shows the previously agreed-upon deliverables and plans for gaining formal acceptance for them
  13. Work Performance Data

    • From the Direct and Manage Work Control Process
    • To assess how well product deliverables are meeting the requirements

Imagens e arquivos do mapa

  • SAB5#48_Validate_Scope

Informações

Descrição
Mapa Mental sobre SAB5#48_Validate_Scope, criado por Israel Miranda Torres em 11-04-2015.
Visualizações
2
Histórico
  • Criado por Norberto C · 11 abr 2015
  • Copiado por Norberto C · 11 abr 2015
  • Copiado por Israel Miranda Torres · 11 abr 2015
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?