  1. Activities defined and sequenced

  2. Resources are identified (type and quantity)

  3. Resources calendars

  4. OPAs (Past project calendars, scheduling methodology, lessons learned)

  5. EEFs (estimating software / productivity metrics)

  6. Risks / Assumptions / Constraints should be reflected in estimations

  7. One-Point Estimating (button up)

    • Submit ONE estimate per activity
    • It can lead people into padding their estimates
    • It hides important information (risks uncertainties)
    • Based on Expert Judgment or Historical Data
    • Done by the responsible of the activity
  8. Analogous Estimating (top down)

    • Time and Cost
    • Based on Expert Judgment or Historical Data
    • Project of task level
    • Compare data with previous projects (similar tasks)
  9. Parametric estimating

    • Based on historical records: Previous projects / Industry requirements, standards, metrics
    • 1 Regression analysis: Compares two variables to see if they are related
    • 2 Learning curve: Time will be less as efficiency improves (due to repetition)
  10. Three point estimating

    • Estimations given are: Optimistic (O), Pessimistic (P) and Most Likely (M)
    • Triangular distribution (simple average) = (P+O+M) / 3
      • 3 scenarios are equal
    • Beta distribution (weighted average) = (P + 4M + O) / 6
      • Oriented to Most Likely scenario
      • Takes into consideration the benefits of risk management
    • Activity standard deviation = (P - O) / 6

Informationen

Beschreibung
Mindmap am SAB6#59_Types_Estimations, erstellt von Beto L am 13/06/2015.
Erstellt von
Beto L · Jun 2015
Aktualisiert
19 Feb 2016
Aufrufe
9
Bewertung

Mehr zu Estimating Activity Resources and Durations

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck