S I T E (ABANDONED

Patrick Stitch Englisch

Inhalt der Mindmap

S I T E (ABANDONED

  1. SITE POSSESSION MEETING

    • PURPOSE
      • For employers to officially hand over possession of the site to the contractor.
        • For the contractors in reciprocation to officially take over possession of the site from the employer for the purpose of the contract.
          • To introduce team members.
            • Explanation of contractor requirements.
    • TIMING
      • - The date of site possession stipulated [Clause 38(b) JKR 203A (REV 10/83)]
      • - Date of commencement of contract corresponding with the date of site possession, e.g. Clause 21.1 PAM 1998 form (With quantities edition)
    • MINUTES TAKER
      • Superintending Officer (SO)
    • PARTICIPANTS
      • Architects - Surveyors (Quantity Surveyors, Land Surveyors, Building Surveyors) - Engineers (C&S) - Contractors - Consultants - Clients
    • EXPLANATION OF CONTRACT REQUIREMENTS
      • Restrictions
        • Use of foreign labour
        • Hours of work
        • Noise
        • Movement of workers
      • Protection of adjoining works
        • Existing property
        • Underground services
        • Unfixed materials & goods
      • Safety issues
        • Methods of working
        • Safety of workman
        • Safety of public
      • Site facilities
        • Temporary site services
        • Fabrication yards
        • Store
        • Site offices
        • Worker's accommodation
    • SETTING OUT PROCEDURES COVERING
      • Documents submittal & approval
        • Work programme
        • Shop drawings
        • Method statements
      • Sample submittal & approval
      • Inspection of work(Quality Assurance/Quality Control matter)
      • Health & safety overseeing
      • Administration of payments
        • Interim valuations
        • Certifications
      • Claim procedures
        • Direct loss & expense
        • Variation works
        • Extension of time
      • Resolution of doubts, ambiguities & requests for information
      • Progress reporting & monitoring
        • Site records
        • Progress reports
      • Security & administrative issues
        • Included delivery & removal of material from site
      • Other procedures directly impacting on the administration of the contract in question
    • INTRODUCTION OF PROJECT TEAM
      • 1. Design Team ( Architect & Surveyor )
      • 2. Structure / Engineering Team ( Civil Engineering , Electrical Engineering , Mechanical Engineering )
      • 3. Implementation Team ( Main Contractor , Sub-contractor , Suppliers )
      • 4. Regulation Bodies/Government /Local Authorities
    • HANDLING OVER VARIOUS DOCUMENTS
      • By Employer
        • 1.Letter of delegation of power
        • 2. Copy of formal contract document
        • 3. Price bill of quantities and set of construction drawing
        • 4. Price summary of price, specification and construction drawing
        • 5. Copy of project procedure manual
        • 6. Copy of approved main contractor work programme to NSC
      • By Contractor
        • 1. Insurance policy or cover note and receipt of premium paid
        • 2. Performance bond, advance payment bond
        • 3. Copy of proposed work programme
        • 4. List of document required from employer/ contract administrator
        • 5. Project and site organization chart, detail and CV of personnel
        • 6. List of proposed sub-contractor
        • 7. Detail of address for service of notice
        • 8. Miscellaneous document required under contract

Informationen

Beschreibung
Mindmap am S I T E (ABANDONED, erstellt von Patrick Stitch am 18/09/2017.
Erstellt von
Patrick Stitch
Aufrufe
1
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck