Chapter 6: Developing a Project Plan
Free Slack vs. Total Slack
- Free Slack is the number of days that an activity can have before it starts delaying the next (successor) activity
- Total Slack is the number of days that activity can have before it starts delaying the whole project.
Importance of Managing the Critical Path
- helps you keep your project on track and on budget, providing visibility into your project
- Dependencies
- people
- tasks
Early vs. Late Slack
- Start Slack is (Late Start - Early Start)
- Finish Slack is (Late Finish - Early Finish)
Level of Detail
- Activities must be clearly defined, and should be measurable
- activity at the lowest level should be clearly identifiable and measurable
Informationen
- Beschreibung
- Mindmap am Chapter 6: Developing a Project Plan, erstellt von John Sullivan am 19/11/2018.
- Erstellt von
- John Sullivan
- Aufrufe
- 0
- Bewertung
Mehr zu Project Management Plan