Chapter 6: Developing a Project Plan

John Sullivan Englisch

Inhalt der Mindmap

Chapter 6: Developing a Project Plan

  1. Free Slack vs. Total Slack

    • Free Slack is the number of days that an activity can have before it starts delaying the next (successor) activity
    • Total Slack is the number of days that activity can have before it starts delaying the whole project.
  2. Importance of Managing the Critical Path

    • helps you keep your project on track and on budget, providing visibility into your project
    • Dependencies
    • people
    • tasks
  3. Early vs. Late Slack

    • Start Slack is (Late Start - Early Start)
    • Finish Slack is (Late Finish - Early Finish)
  4. Level of Detail

    • Activities must be clearly defined, and should be measurable
    • activity at the lowest level should be clearly identifiable and measurable

Informationen

Beschreibung
Mindmap am Chapter 6: Developing a Project Plan, erstellt von John Sullivan am 19/11/2018.
Erstellt von
John Sullivan
Aufrufe
0
Bewertung

Mehr zu Project Management Plan

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck