Introduction
- Project plan must include a schedule for start and end times of each activity
- Ensures resource availability
- Avoid activities competing for resources
- indicate which staff does which activity
- Produce baseline to measure actual against
- Cash flow forecast
- Replan project to correct drift from target
- Activity plan provides a target start and end date for each activity
- Try have each activity produce a deliverable product or tangible outcome
- Project plan must include a schedule for start and end times of each activity
6.2 Objectives of activity plan
- Feasibility assessment
- Chapter 5 -> is the project possible in time frame and resource constraints
- Resource allocation
- Most effective resource allocation to the project
- Detailed costing
- How much will project cost and when is the expense incurred
- Motivation
- Providing targets. Monitoring actuals against targets
- Co-ordination SPM (5e)
- Coordinating different staff to be available for work
- Completing the project at a minimum time at an acceptable cost
- Indicate the implications on the time scale by adding constraints -> such as quality requirements
- Planning continues at each stage from the beginning to product delivery
- Feasibility assessment
6.4 Project schedules
- Project plan must indicate start and end dates and resources -> It then becomes a project schedule
- Start with a ideal activity plan -> no constraints on resources
- Ideal activity plan -> Step 6 identifies the risks of activity
- Step 7 -> resource allocation -> might affect ideal plan as there is no resource constraints -> ideal plan might need to be adapted to include resource availability
- Step 8 -> Schedule production -> Start and end dates of activities and resource allocations
6.5 Projects and activities
- Defining Project
- Interrelated activities
- Starts when at least one activity can begin
- Complete when all activities complete
- Activity has start and end and defines a deliverable
- Activity requires resources
- Duration of activity must be forecastable
- Activities may be dependent on one another
- Identify activities
- activity based approach
- Create list of all activities in project
- Use brainstorming
- Generate a WBS which identifies the high level tasks
- Each WBS branch has activities which collectively complete the WBS nodes
- Advantages -> Likely for tasks catalogue to be complete, and non-overlapping activities
- Only the leaves are activities
- Figure 1: A fragment of an activity-based work breakdown structure
- product based approach
- Chapter 2
- Product Breakdown Structure (PBS) and a Product Flow Diagram (PFD)
- PFD -> Which other products are required as inputs for other product
- PFD can be transformed to list of activities by determining transformations of one product to the other
- Advantage - > Less likely a product is omitted from PBS
- Useful for methodologies -> SSADM and USDP
- Figure 2: product based approach
- Chapter 2
- hybrid approach
- Hybrid Approach based on deliverables and activities
- 5 levels of WBS according to IBM
- Level 1 -> Project
- Level 2 - > Deliverables such as software, manuals and training course
- Level 3 -> Components -> key work items needed to produce deliverables
- Level 4 -> Work packages ->major work items or collections of related tasks
- Level 5 -> Tasks normally for a single person
- activity based approach
- Defining Project
6.6 Sequencing and scheduling activities
- Sequence activities based on logical relationships
- Schedule activities -> taking into account resources
6.7 Network planning models
- Scheduling technique -> models activities and relationships as a network
- Network's time flows left to right
- Best know techniques in this area -> Critical Path Method (CPM) and Program Evaluation Review Technique (PERT)
- Both use activity on arrow approach to visualise project as network
- Activities are drawn as arrows
- Arrows join circles -> circles are start and/or end end of activity or set of activities
- A variation of technique is -> precedence network
- Method -> Activity on node networks
- Activities -> are nodes
- Links between nodes -> precedence (sequencing)
6.8 Formulating a network model
- Network has one start node
- Network has one end node
- Each activity has a time
- Nodes have not execution time
- Flow from left to right
- Nodes are numbered
- Loop free network
- Dangle free network
- how to representing lagged activities
- Staggered activities in parallel
- Lag is represented on the linking arrow in days -> when it starts and when it ends
- Hammock activities -> have zero duration
- Start with first hammocked activity and ends with last
- Can represent over head costs or resources used at constant over actvities
- Labeling conventions
6.9 Adding the time dimension
- When dependencies are identified and the logical network model is drawn
- CPM -> concerned with completing the project ASAP and Identifying the activities which will cause a delay (critical path)
- Each activity requires a duration
- Forward pass -> calc earliest dates activities can commence and be completed
- If actual start date known -> can use actual dates, otherwise use days/weeks
- Activities start at the end of week 0 or begin of week 1 (same thing)
- Activity A, B and F can start immediately
- A -> 6 weeks, earliest finish is 6 weeks
- B -> 4 weeks, earliest 4 weeks, and for F -> 10 weeks
- C -> earliest start is 6 weeks, earliest finish is week 9
- E, H and G can start after its longest dependency
- Backward pass -> calc latest dates activities can start and the critical path
- We assume that latest completion date is same as earliest completion date
- Completion for G and H is week 13
- H -> latest start week 11 (13-2)
- G -> Latest start week 10 (13-3)
- C -> Latest completion is start of H
- E and F -> latest end is week 10
- Identify the critical path
- One path of successive activities which define duration of project
- Activity float (middle number)-> Difference between activity earliest start and latest start or earliest finish and latest finish
- When the float is zero it is on the critical path
- Activity span -> maximum allowed time for activity
- Difference between earliest start and latest end
6.13 Activity float
- Measures of activity float
- Free float -> Activity may be delayed by time frame which doesn't affect other sub activities
- Difference between earliest completion date and earliest start of subsequent activity
- Interfering float -> Difference between total float and free float
- Once free float is used or zero this float tells us how much activity can be delayed without delaying project end date, but delay the start dates of subs
- Free float -> Activity may be delayed by time frame which doesn't affect other sub activities
- Don't issue total float as Activity A using 2 weeks float, leaves activity B with no float. hence critical path time
- Measures of activity float
6.14 Shorter project duration
- Add resources, reduce the critical path durations
Activity on Arrow networks
- Same rules as network nodel
- Dummy activities
- When two paths have a common dependency but are in other aspect mutually exclusive
- Lagged activities
- Have to use pairs of dummy activities
- Labelling
Bilder und Dateien der Mindmap
Informationen
- Beschreibung
- Computer Science Mindmap am Chapter 6: Activity planning (3708), erstellt von Gideon Van am 26/03/2019.
- Erstellt von
- Gideon Van
- Aufrufe
- 4
- Bewertung