GoConqr hat ein neues Design! Sag uns, wie es dir gefällt.

Mindmap

SAB9#70_Control Costs

Salvador Rueda Englisch

SAB9#70_Control Costs

Inhalt der Mindmap

SAB9#70_Control Costs

  • In the exam, assume that the project manager is measuring, measuring, measuring on the project 
  1. It is all about knowing how you are doing compared to your plan and making adjustments when necessary

  2. Project funding requirements

  3. Project Management Plan

  4. Work Performance Data

  5. Orginizational Process Assets

  6. Earned value management

  7. Project Management Software

  8. Reserve Analysis

  9. To-complete performance index (TCPI)

  10. Performance Reviews

    • Earned Value Management
      • Integrates COST, TIME and the WORK DONE
      • PV - Planned Value
      • EV - Erned Value
      • AC - Actual Cost (total cost)
      • BAC - Budget at Completion
      • EAC - Estimate at Completion
      • ETC - Estimate to Complete
      • VAC - Variance at Completion
      • Formulas
        • CV -Cost Variance EV - AC
        • SV - Schedule Variance EV - PV
        • CPI - Cost Performance Index EV/AC
          • The CPI is a cumulative because it is using costs to date. It could be written as CPI(c)=EV(c)/AC(c)
        • SPI - Schedule Performance Index EV/PV
        • EAC Estimate at Completion
          • AC + Bottom-up ETC
          • BAC/CPI
          • AC+(BAC-EV)
          • AC+(bac-EV)/CPI(c)XSPI(c))
        • TCPI - To-Complete Performance Index (BAC-EV)/(BAC-AC)
        • ETC - Estimate to Complete EAC-AC
        • VAC - Variance al Complietion BAC-EAC
  11. Forecasting

  12. Work Performance Information

    • CV - Cost Variance
    • SV - Schedule Variance
    • CPI - Cost Performance Index
    • SPI - Schedule Performance Index
    • TCPI - To-Complete Performance Index
    • EAC - Estimate to Complete
    • VAC - Variance al Complietion
  13. Cost Forecast

  14. Change request

  15. Update Management Plan

  16. Update Project Documents

  17. Update OPA´s

  18. Progess Reporting

Bilder und Dateien der Mindmap

  • SAB9#70_Control Costs
  • SAB9#70_Control Costs
  • SAB9#70_Control Costs
  • SAB9#70_Control Costs

Informationen

Beschreibung
Mindmap am SAB9#70_Control Costs, erstellt von Salvador Rueda am 25/02/2016.
Erstellt von
Salvador Rueda
Aufrufe
26
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck