O GoConqr está de visual novo! Conte para nós o que você achou.

Mapa mental

SAB9#70_Control Costs

Salvador Rueda Inglês

SAB9#70_Control Costs

Conteúdo do mapa

SAB9#70_Control Costs

  • In the exam, assume that the project manager is measuring, measuring, measuring on the project 
  1. It is all about knowing how you are doing compared to your plan and making adjustments when necessary

  2. Project funding requirements

  3. Project Management Plan

  4. Work Performance Data

  5. Orginizational Process Assets

  6. Earned value management

  7. Project Management Software

  8. Reserve Analysis

  9. To-complete performance index (TCPI)

  10. Performance Reviews

    • Earned Value Management
      • Integrates COST, TIME and the WORK DONE
      • PV - Planned Value
      • EV - Erned Value
      • AC - Actual Cost (total cost)
      • BAC - Budget at Completion
      • EAC - Estimate at Completion
      • ETC - Estimate to Complete
      • VAC - Variance at Completion
      • Formulas
        • CV -Cost Variance EV - AC
        • SV - Schedule Variance EV - PV
        • CPI - Cost Performance Index EV/AC
          • The CPI is a cumulative because it is using costs to date. It could be written as CPI(c)=EV(c)/AC(c)
        • SPI - Schedule Performance Index EV/PV
        • EAC Estimate at Completion
          • AC + Bottom-up ETC
          • BAC/CPI
          • AC+(BAC-EV)
          • AC+(bac-EV)/CPI(c)XSPI(c))
        • TCPI - To-Complete Performance Index (BAC-EV)/(BAC-AC)
        • ETC - Estimate to Complete EAC-AC
        • VAC - Variance al Complietion BAC-EAC
  11. Forecasting

  12. Work Performance Information

    • CV - Cost Variance
    • SV - Schedule Variance
    • CPI - Cost Performance Index
    • SPI - Schedule Performance Index
    • TCPI - To-Complete Performance Index
    • EAC - Estimate to Complete
    • VAC - Variance al Complietion
  13. Cost Forecast

  14. Change request

  15. Update Management Plan

  16. Update Project Documents

  17. Update OPA´s

  18. Progess Reporting

Imagens e arquivos do mapa

  • SAB9#70_Control Costs
  • SAB9#70_Control Costs
  • SAB9#70_Control Costs
  • SAB9#70_Control Costs

Informações

Descrição
Mapa Mental sobre SAB9#70_Control Costs, criado por Salvador Rueda em 25-02-2016.
Criado por
Salvador Rueda
Visualizações
26
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?