SAB11#47_49 Controlling Scope & Control Scope
Inhalt der Mindmap
SAB11#47_49 Controlling Scope & Control Scope
- It’s how you make sure that you make only those changes to the scope that you need to make, and that everyone is clear on what the consequences of those changes are.
- The goal of Control Scope is updating the scope, plan, baseline, and WBS info.
Work performance data
- It tell´s how well the team is doing the job
Work performance information
- These updates are how you react to necessary scope changes that are approved through change control.
Requirements traceability matrix
Requirements documentation
Project Management plan
Updates to organizational process assets
Project document updates
Updates to the Project Management plan
Change requests
Variance analysis
- This is where you constantly compare the information that you’re gathering about. the way the project’s going to affect your baseline.
- A change is needed.
- Create a change request.
- Get the change approved.
- Do variance analysis.
- Replan the work.
- Create a new baseline.