SAB11#47_49 Controlling Scope & Control Scope

  • It’s how you make sure that you make only those changes to the scope that you need to make, and that everyone is clear on what the consequences of those changes are.
  • The goal of Control Scope is updating the scope, plan, baseline, and WBS info.
  1. Work performance data

    • It tell´s how well the team is doing the job
  2. Work performance information

    • These updates are how you react to necessary scope changes that are approved through change control.
  3. Requirements traceability matrix

  4. Requirements documentation

  5. Project Management plan

  6. Updates to organizational process assets

  7. Project document updates

  8. Updates to the Project Management plan

  9. Change requests

  10. Variance analysis

    • This is where you constantly compare the information that you’re gathering about. the way the project’s going to affect your baseline.
    • A change is needed.
    • Create a change request.
    • Get the change approved.
    • Do variance analysis.
    • Replan the work.
    • Create a new baseline.

Información

Descripción
p Taller de Certificación de PMP Mapa Mental sobre SAB11#47_49 Controlling Scope & Control Scope, creado por Omar Arce el 25/06/2016.
Creado por
Omar Arce
Visitas
16
Valoración

Más sobre Control Scope

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?