  1. contractor late completing a contract is in breach and may need 2 pay damages

    • 2 types
      • liquidated
      • unliquidated
  2. Damages in contracts

    • JCT
      • JCT SBC/IC/Prime Cost
        • LD's are inputted into the contract particulars
        • inc 4 sectional completion damages
        • no cap on LD's
        • ddt from sums due to contractor/
        • Non-completion cert must be issued as must appropriate payment notices
      • JCT Management Bdg contract
        • LD's are inputted into the contract particulars
        • inc 4 sectional completion damages
        • no cap on LD's
        • ddt from sums due to contractor
        • Non-completion cert must be issued as must appropriate payment notices
      • JCT D&B
        • LD's are inputted into the contract particulars
        • inc 4 sectional completion damages
        • Total liability does not apply 2 or is not affected by LD provisions
        • ddt from sums due to contractor
        • Non-completion cert must be issued as must appropriate payment notices
      • JCT MW
        • LD's are inputted into the contract particulars
        • No sectional completion damages
        • no cap on LD's
        • ddt from sums due to contractor
        • No provision 4 partial possession & non-completion certificate if NOT REQUIRED
      • JCT Mgm contract
        • Damages are Unliquidated
        • LD's not entered into the contract
        • No sectional completion damages
        • Cap on LD is irrelevant
        • ddt from sums due to contractor
        • No provisional for partial posession
    • NCE ECC
      • NEC ECC Option A to F
        • Delay damages are inputted in contract data Pt 1
        • inc 4 sectional completion damages
        • no cap on DD's the guidance book implies the standard contract data can be amended
        • Inc in PM certificate 2 MC & emp.
        • interest applicable if damages deducted and sub the completion date is revised. if delay damages is an optional clause is NOT selected then damages will be unliquidated
    • FIDIC
      • FIDIC red book
        • Delay damages are inputted in appendix to tende
        • inc 4 sectional completion damages
        • Enter text here
      • FIDIC Orange

Informationen

Beschreibung
T017 & T016 Mindmap am T017 L&AD, erstellt von alison_patey0437 am 06/05/2013.
Erstellt von
alison_patey0437
Aufrufe
126
Bewertung

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck