  1. 11. What is the critical path of the network described in the following table?

    Bild zu Frage 1
    1. Aa. A, D, G, Finish
    2. Bb. B, D, F, Finish
    3. Cc. C, E, G, Finish
    4. Dd. B, E, G, Finish
  2. 22. What is the effect on the finish date if Activity E, in the previous question, is two days late?
    1. Aa. No effect.
    2. BB. Slips 1 day.
    3. Cc. Slips 2 days.
    4. Dd. Slips 3 days.
  3. 3Several tools and techniques are named for estimating resources - all the following
    EXCEPT:
    1. Aa. Resource pool.
    2. Bb. Expert judgment.
    3. Cc. Alternatives analysis.
    4. Dd. Published estimating data.
  4. 4The project team has developed the project schedule. What needs to be done before finalizing it?
    1. Aa. Distribute the project schedule according to the communications plan.
    2. Bb. Save it as the time baseline.
    3. Cc. Confirm the availability of resources.
    4. Dd. Submit it to the project sponsor and/or other responsible individuals for approval.
  5. 5PMBOK@ Guide states that the Estimate Resource process is 'closely coordinated with' the Estimate Costs process. The Course states that resource estimating cannot be done independently from a still different process. Which one is that?
    1. Aa. Sequence Activities.
    2. Bb. Estimate Durations.
    3. Cc. Plan Quality.
    4. Dd. Identify Risks.
  6. 6A likely result of fast tracking, in addition to hoped-for shortening of the project schedule, is:
    1. Aa. Fewer resources.
    2. Bb. Increased risk.
    3. Cc. Lower costs.
    4. Dd. Greater control.
  7. 7One of the tools & techniques listed for activity resource estimating is project management software. What feature of such software would be most applicable?
    1. Aa. Resource pool.
    2. Bb. Scheduling.
    3. Cc. Resource calendars.
    4. Dd. Activity dependencies.
  8. 88. A primary benefit of critical chain scheduling is:
    1. Aa. Individual estimates do not contain excess time.
    2. Bb. Resource leveling is not necessary.
    3. Cc. Schedules are more realistic because buffers are pooled rather than allocated Individually to each activity.
    4. Dd. Activities are scheduled as late as possible.
  9. 99. What issue is most important in making three-point estimates?
    1. Aa. The probability curve to be applied.he probability curve to be applied.
    2. Bb. Interruptions.
    3. Cc. The number of people involved in making the estimates.
    4. Dd. How well the activities are understood.
  10. 1010. What tool or technique is useful for conducting analysis of the impact of a strike during project execution?
    1. Aa. Monte Carlo.
    2. Bb. Applying leads & lags.
    3. Cc. Lateral thinking.
    4. Dd. Resource leveling.

Informationen

Beschreibung
Quiz am SEGMENT 6 QUIZ, erstellt von brandon mayo am 09/10/2017.
Sprache
English
Aufrufe
3
Schlagwörter
pmp
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck