Highway Engineering 1 Lecture 3

Pauline Leota 32 Fragen

Quiz starten

Fragen in diesem Quiz (32)

  1. 1What is the New Zealand standard for Conditions of contract for building and civil engineers?
    1. ANZS 1170.0
    2. BNZS 3910:2013
    3. CNZS 3101:2008
  2. 2What does the NZS3910 include?
    1. AStandard form of general conditions of contract for incorporation into construction contract documents
    2. BIncludes specific provisions on programmes, safety plans, quality plans and traffic management plans
    3. CAll of the above
  3. 3The "schedule of prices" is not known as the "bill of quantities"
    1. ARichtig
    2. BFalsch
  4. 4What are the project process a typical engineering project follows in sequence?
    1. AInception, feasibility, Design, Consenting, Tendering, Construction, Commissioning
    2. BFeasibility, Inception, Design, Tendering, consenting, Construction, Commissioning
    3. CCommissioning, Designing, Tendering, Consenting, Inception, Feasibility, Design
  5. 5What is tendering?
    1. AThe contractor must make sure they understand the project works and ensure the price covers all the required works
    2. BThe contractor has to develop a plan of how the work will be done, what resources are required, and what it will all cost with the contractor,
  6. 6What is involved in Pre-establishment?
    1. ABonds and Insurances
    2. BSet up meetings
    3. CProject planning
    4. DAll of the above
  7. 7Project planning is how the works are to be carried out, what resources (plant, equipment and labour) are needed and when, what materials are needed, what materials are required and when they are needed, what subcontractors are required, any other processes that need to be undertaken to complete the works.
    1. ARichtig
    2. BFalsch
  8. 8What types of management plans are there for the project?
    1. ATraffic Management plan
    2. BEnvironmental Protection plan
    3. CAnger management plan
    4. DEating plan
    5. EHealth and Safety Plan
    6. FQuality Management Plan
  9. 9What is involved in Establishment?
    1. AContractor given possession of the site by Engineer
    2. BEstablishing Access
    3. CConstruction site facilities
    4. DBringing plant and equipment to site
    5. EAll of the above
  10. 10Site access needs to be designed to ensure construction traffic can safely enter and leave the site.Bild zu Frage 10
    1. ARichtig
    2. BFalsch

Informationen

Beschreibung
Diploma Highway Engineering 1 Quiz am Highway Engineering 1 Lecture 3 , erstellt von Pauline Leota am 12/05/2015.
Sprache
English
Aufrufe
3
Schlagwörter
nzs 3910:2013site layout and establishmenttnz f/1highway engineering 1 diploma
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Was sollen wir als Nächstes hinzufügen?