Fragen in diesem Quiz (27)
1The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.
- ARichtig
- BFalsch
2Too many parallel activities for one individual is an example of a resource constraint.
- ARichtig
- BFalsch
3The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.
- ARichtig
- BFalsch
4Resource leveling or smoothing is only used on projects which are resource constrained.
- ARichtig
- BFalsch
5Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
- ARichtig
- BFalsch
6The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
- ARichtig
- BFalsch
7In a resource-constrained project, the completion date is most likely to change.
- ARichtig
- BFalsch
8Having too few programmers and too many engineers is an example of a people resource constraint.
- ARichtig
- BFalsch
9If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.
- ARichtig
- BFalsch
10A lack of readily available engineers is a technical constraint.
- ARichtig
- BFalsch
11Resource dependency takes priority over technological dependency but it does not violate it.
- ARichtig
- BFalsch
12To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
- ARichtig
- BFalsch
13Sequential activities hold just as much potential for resource conflicts as parallel activities.
- ARichtig
- BFalsch
14All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
- ARichtig
- BFalsch
15Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.
- ARichtig
- BFalsch
16Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.
- ARichtig
- BFalsch
17When resource constraints are added to technical constraints the original project network may change as well as the completion date.
- ARichtig
- BFalsch
18When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
- ARichtig
- BFalsch
19A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. We can assume that everything is going as planned and that we are under budget.
- ARichtig
- BFalsch
20Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.
- ARichtig
- BFalsch
21Without a time-phased budget a good project schedule and cost control are impossible.
- ARichtig
- BFalsch
22If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule.
- ARichtig
- BFalsch
23Project managers should always assign the best people to the most difficult tasks.
- ARichtig
- BFalsch
24Resource constraints can be overcome by creative and efficient scheduling.
- ARichtig
- BFalsch
25Project management software is important because it will manage the project for the project manager.
- ARichtig
- BFalsch
26Comparing Planned Costs versus Actual Costs will give the project manager a quick understanding of the status of the project.
- ARichtig
- BFalsch
27Having individual staff members assigned to multiple simultaneous tasks is an efficient way to split tasks and get tasks accomplished more efficiently.
- ARichtig
- BFalsch
Informationen
- Beschreibung
- Quiz am CH8 T/F, erstellt von shamuz ALI am 01/04/2019.
- Autor
- shamuz ALI
- Sprache
- English
- Aufrufe
- 0
- Bewertung
- Noch keine Bewertungen Bewerte dieses Quiz