1The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.
- ATrue
- BFalse
2Too many parallel activities for one individual is an example of a resource constraint.
- ATrue
- BFalse
3The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.
- ATrue
- BFalse
4Resource leveling or smoothing is only used on projects which are resource constrained.
- ATrue
- BFalse
5Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.
- ATrue
- BFalse
6The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.
- ATrue
- BFalse
7In a resource-constrained project, the completion date is most likely to change.
- ATrue
- BFalse
8Having too few programmers and too many engineers is an example of a people resource constraint.
- ATrue
- BFalse
9If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.
- ATrue
- BFalse
10A lack of readily available engineers is a technical constraint.
- ATrue
- BFalse
11Resource dependency takes priority over technological dependency but it does not violate it.
- ATrue
- BFalse
12To determine if a project is time-constrained or resource-constrained you would consult the project priority matrix.
- ATrue
- BFalse
13Sequential activities hold just as much potential for resource conflicts as parallel activities.
- ATrue
- BFalse
14All leveling techniques delay noncritical activities by using positive slack to smooth out the resource requirements.
- ATrue
- BFalse
15Since resource leveling or smoothing delays noncritical activities, a common result is a decrease in network sensitivity.
- ATrue
- BFalse
16Scheduling projects classified as resource-constrained focuses on completing the project as soon as possible under the given resource constraints.
- ATrue
- BFalse
17When resource constraints are added to technical constraints the original project network may change as well as the completion date.
- ATrue
- BFalse
18When scheduling activities in a resource-constrained project typically the activity scheduled first has the most amount of slack.
- ATrue
- BFalse
19A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. We can assume that everything is going as planned and that we are under budget.
- ATrue
- BFalse
20Splitting is a scheduling technique used to get a better schedule or better resource utilization and should be used without hesitation.
- ATrue
- BFalse
21Without a time-phased budget a good project schedule and cost control are impossible.
- ATrue
- BFalse
22If resources are truly limited and activity time estimates are accurate, the resource-constrained schedule will materialize as the project is implemented, not the time-constrained schedule.
- ATrue
- BFalse
23Project managers should always assign the best people to the most difficult tasks.
- ATrue
- BFalse
24Resource constraints can be overcome by creative and efficient scheduling.
- ATrue
- BFalse
25Project management software is important because it will manage the project for the project manager.
- ATrue
- BFalse
26Comparing Planned Costs versus Actual Costs will give the project manager a quick understanding of the status of the project.
- ATrue
- BFalse
27Having individual staff members assigned to multiple simultaneous tasks is an efficient way to split tasks and get tasks accomplished more efficiently.
- ATrue
- BFalse
Information
- Description
- Quiz on CH8 T/F, created by shamuz ALI on 01/04/2019.
- Author
- shamuz ALI
- Language
- English
- Views
- 0
- Rating
- No ratings yet Rate this quiz