Ch 18 n 19 comp

Beschreibung

319 test stuffs
buggq
Quiz von buggq, aktualisiert more than 1 year ago Mehr Weniger
eabrown6
Erstellt von eabrown6 vor etwa 8 Jahre
buggq
Kopiert von buggq vor etwa 8 Jahre
226
0

Zusammenfassung der Ressource

Frage 1

Frage
At December 31, 2015, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $14,400,000 due to unanticipated price increases. What is the total amount of Construction Expenses that Seasons will recognize for the year ended December 31, 2015?
Antworten
  • $10,800,000
  • $6,300,000
  • $6,390,000
  • $6,540,000

Frage 2

Frage
At December 31, 2015, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $14,400,000 due to unanticipated price increases. What is reported in the balance sheet at December 31, 2015 for Seasons as the difference between the Construction in Process and the Billings on Construction in Process accounts, and is it a debit or a credit? Difference between the accounts Debit/Credit
Antworten
  • $3,380,000 Credit
  • $1,240,000 Debit
  • $880,000 Debit
  • $1,240,000 Credit

Frage 3

Frage
Seasons Construction completes the remaining 25% of the building construction on December 31, 2016, as scheduled. At that time the total costs of construction are $15,000,000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Seasons will recognize for the year ended December 31, 2016? Revenue Expenses
Antworten
  • $14,880,000 $15,000,000
  • $3,720,000 $ 3,750,000
  • $3,720,000 $ 4,200,000
  • $3,750,000 $ 3,750,000

Frage 4

Frage
Cooper Construction Company had a contract starting April 2015, to construct a $18,000,000 building that is expected to be completed in September 2017, at an estimated cost of $16,500,000. At the end of 2015, the costs to date were $7,590,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $3,600,000 and the cash collected during 2015 was 2,400,000. For the year ended December 31, 2015, Cooper would recognize gross profit on the building of:
Antworten
  • $632,500
  • $690,000
  • $810,000
  • $0

Frage 5

Frage
Cooper Construction Company had a contract starting April 2015, to construct a $18,000,000 building that is expected to be completed in September 2017, at an estimated cost of $16,500,000. At the end of 2015, the costs to date were $7,590,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $3,600,000 and the cash collected during 2015 was 2,400,000. At December 31, 2015 Cooper would report Construction in Process in the amount of:
Antworten
  • $690,000
  • $7,590,000
  • $8,280,000
  • $7,080,000

Frage 6

Frage
Hayes Construction Corporation contracted to construct a building for $4,500,000. Construction began in 2014 and was completed in 2015. Data relating to the contract are summarized below: Year ended December 31, 2014 2015 Costs incurred $1,800,000 $1,350,000 Estimated costs to complete 1,200,000 — Hayes uses the percentage-of-completion method as the basis for income recognition. For the years ended December 31, 2014, and 2015, respectively, Hayes should report gross profit of
Antworten
  • $810,000 and $540,000.
  • $2,700,000 and $1,800,000.
  • $900,000 and $450,000.
  • $0 and $1,350,000.

Frage 7

Frage
Monroe Construction Company uses the percentage-of-completion method of accounting. In 2015, Monroe began work on a contract it had received which provided for a contract price of $25,000,000. Other details follow: 2015 Costs incurred during the year $12,000,000 Estimated costs to complete as of December 31 8,000,000 Billings during the year 11,000,000 Collections during the year 6,500,000 What should be the gross profit recognized in 2015?
Antworten
  • $1,000,000
  • $13,000,000
  • $3,000,000
  • $5,000,000

Frage 8

Frage
In 2015, Fargo Corporation began construction work under a three-year contract. The contract price is $4,800,000. Fargo uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2015, follow: Balance Sheet Accounts receivable—construction contract billings $200,000 Construction in progress $600,000 Less contract billings 480,000 Costs and recognized profit in excess of billings 120,000 Income Statement Income (before tax) on the contract recognized in 2015 $120,000 How much cash was collected in 2015 on this contract?
Antworten
  • $200,000
  • $280,000
  • $40,000
  • $480,000

Frage 9

Frage
In 2015, Fargo Corporation began construction work under a three-year contract. The contract price is $4,800,000. Fargo uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2015, follow: Balance Sheet Accounts receivable—construction contract billings $200,000 Construction in progress $600,000 Less contract billings 480,000 Costs and recognized profit in excess of billings 120,000 Income Statement Income (before tax) on the contract recognized in 2015 $120,000 What was the initial estimated total income before tax on this contract?
Antworten
  • $600,000
  • $640,000
  • $800,000
  • $960,000

Frage 10

Frage
Adler Construction Co. uses the percentage-of-completion method. In 2014, Adler began work on a contract for $6,600,000 and it was completed in 2015. Data on the costs are: Year Ended December 31 2014 2015 Costs incurred $2,340,000 $1,680,000 Estimated costs to complete 1,560,000 — For the years 2014 and 2015, Adler should recognize gross profit in 2014 and 2015 of 2014 2015
Antworten
  • $0 $2,580,000
  • $1,548,000 $1,032,000
  • $1,620,000 $960,000
  • $1,620,000 $2,580,000

Frage 11

Frage
Gomez, Inc. began work in 2014 on contract #3814, which provided for a contract price of $14,400,000. Other details follow: 2014 2015 Costs incurred during the year $2,400,000 $7,350,000 Estimated costs to complete, as of December 31 7,200,000 0 Billings during the year 2,700,000 10,800,000 Collections during the year 1,800,000 11,700,000 Assume that Gomez uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2014 is
Antworten
  • $900,000.
  • $1,200,000.
  • $3,600,000.
  • $4,800,000.

Frage 12

Frage
Kiner, Inc. began work in 2014 on a contract for $16,800,000. Other data are as follows: 2014 2015 Costs incurred to date $7,200,000 $11,200,000 Estimated costs to complete 4,800,000 — Billings to date 5,600,000 16,800,000 Collections to date 4,000,000 14,400,000 If Kiner uses the percentage-of-completion method, the gross profit to be recognized in 2014 is
Antworten
  • $2,880,000.
  • $3,200,000.
  • $4,320,000.
  • $4,800,000.

Frage 13

Frage
Horner Construction Co. uses the percentage-of-completion method. In 2014, Horner began work on a contract for $16,500,000; it was completed in 2015. The following cost data pertain to this contract: Year Ended December 31 2014 2015 Cost incurred during the year $5,850,000 $4,200,000 Estimated costs to complete at the end of year 3,900,000 — The amount of gross profit to be recognized on the income statement for the year ended December 31, 2015 is
Antworten
  • $2,400,000.
  • $2,580,000.
  • $2,700,000.
  • $6,450,000.

Frage 14

Frage
Horner Construction Co. uses the percentage-of-completion method. In 2014, Horner began work on a contract for $16,500,000; it was completed in 2015. The following cost data pertain to this contract: Year Ended December 31 2014 2015 Cost incurred during the year $5,850,000 $4,200,000 Estimated costs to complete at the end of year 3,900,000 — If the completed-contract method of accounting was used, the amount of gross profit to be recognized for years 2014 and 2015 would be 2014 2015
Antworten
  • $6,750,000. $0.
  • $6,450,000. $(300,000).
  • $0. $6,450,000.
  • $0. $6,750,000.

Frage 15

Frage
Remington Construction Company uses the percentage-of-completion method. During 2014, the company entered into a fixed-price contract to construct a building for Sherman Company for $24,000,000. The following details pertain to the contract: At December 31, 2014 At December 31, 2015 Percentage of completion 25% 60% Estimated total cost of contract $18,000,000 $20,000,000 Gross profit recognized to date 1,500,000 2,400,000 The amount of construction costs incurred during 2015 was
Antworten
  • $12,000,000.
  • $7,500,000.
  • $4,500,000.
  • $2,000,000.

Frage 16

Frage
Eilert Construction Company had a contract starting April 2015, to construct a $21,000,000 building that is expected to be completed in September 2016, at an estimated cost of $19,250,000. At the end of 2015, the costs to date were $8,855,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $4,200,000 and the cash collected during 2015 was $2,800,000. Eilert uses the percentage-of-completion method. For the year ended December 31, 2015, Eilert would recognize gross profit on the building of
Antworten
  • $0.
  • $737,917.
  • $805,000.
  • $945,000.

Frage 17

Frage
Eilert Construction Company had a contract starting April 2015, to construct a $21,000,000 building that is expected to be completed in September 2016, at an estimated cost of $19,250,000. At the end of 2015, the costs to date were $8,855,000 and the estimated total costs to complete had not changed. The progress billings during 2015 were $4,200,000 and the cash collected during 2015 was $2,800,000. Eilert uses the percentage-of-completion method. For the year ended December 31, 2015, Eilert would recognize gross profit on the building of
Antworten
  • $9,660,000.
  • $8,855,000.
  • $8,260,000.
  • $805,000.

Frage 18

Frage
Bruner Constructors, Inc. has consistently used the percentage-of-completion method of recognizing income. In 2014, Bruner started work on a $42,000,000 construction contract that was completed in 2015. The following information was taken from Bruner's 2014 accounting records: Progress billings $13,200,000 Costs incurred 12,600,000 Collections 8,400,000 Estimated costs to complete 25,200,000 What amount of gross profit should Bruner have recognized in 2014 on this contract?
Antworten
  • $4,200,000
  • $2,800,000
  • $2,100,000
  • $1,400,000

Frage 19

Frage
At the beginning of 2015, Pitman Co. purchased an asset for $1,200,000 with an estimated useful life of 5 years and an estimated salvage value of $100,000. For financial reporting purposes the asset is being depreciated using the straight-line method; for tax purposes the double-declining-balance method is being used. Pitman Co.’s tax rate is 40% for 2015 and all future years. At the end of 2015, what are the book basis and the tax basis of the asset? Book basis Tax basis
Antworten
  • $880,000 $620,000
  • $980,000 $620,000
  • $980,000 $720,000
  • $880,000 $720,000

Frage 20

Frage
At the beginning of 2015, Pitman Co. purchased an asset for $1,200,000 with an estimated useful life of 5 years and an estimated salvage value of $100,000. For financial reporting purposes the asset is being depreciated using the straight-line method; for tax purposes the double-declining-balance method is being used. Pitman Co.’s tax rate is 40% for 2015 and all future years. At the end of 2015, which of the following deferred tax accounts and balances is reported on Pitman’s balance sheet? Account _ Balance
Antworten
  • Deferred tax asset $104,000
  • Deferred tax liability $104,000
  • Deferred tax asset $156,000
  • Deferred tax liability $156,000

Frage 21

Frage
Lehman Corporation purchased a machine on January 2, 2013, for $3,000,000. The machine has an estimated 5-year life with no salvage value. The straight-line method of depreciation is being used for financial statement purposes and the following MACRS amounts will be deducted for tax purposes: 2013 $600,000 2016 $345,000 2014 960,000 2017 345,000 2015 576,000 2018 174,000 Assuming an income tax rate of 30% for all years, the net deferred tax liability that should be reflected on Lehman's balance sheet at December 31, 2014 be Deferred Tax Liability Current Noncurrent
Antworten
  • $0 $108,000
  • $7,200 $100,800
  • $100,800 $7,200
  • $108,000 $0

Frage 22

Frage
Mathis Co. at the end of 2014, its first year of operations, prepared a reconciliation between pretax financial income and taxable income as follows: Pretax financial income $ 800,000 Estimated litigation expense 2,000,000 Installment sales (1,600,000) Taxable income $ 1,200,000 The estimated litigation expense of $2,000,000 will be deductible in 2016 when it is expected to be paid. The gross profit from the installment sales will be realized in the amount of $800,000 in each of the next two years. The estimated liability for litigation is classified as noncurrent and the installment accounts receivable are classified as $800,000 current and $800,000 noncurrent. The income tax rate is 30% for all years. The income tax expense is
Antworten
  • $240,000.
  • $360,000.
  • $400,000.
  • $800,000.

Frage 23

Frage
Mathis Co. at the end of 2014, its first year of operations, prepared a reconciliation between pretax financial income and taxable income as follows: Pretax financial income $ 800,000 Estimated litigation expense 2,000,000 Installment sales (1,600,000) Taxable income $ 1,200,000 The estimated litigation expense of $2,000,000 will be deductible in 2016 when it is expected to be paid. The gross profit from the installment sales will be realized in the amount of $800,000 in each of the next two years. The estimated liability for litigation is classified as noncurrent and the installment accounts receivable are classified as $800,000 current and $800,000 noncurrent. The income tax rate is 30% for all years. The deferred tax asset to be recognized is
Antworten
  • $0.
  • $120,000 current.
  • $600,000 current.
  • $600,000 noncurrent.

Frage 24

Frage
Mathis Co. at the end of 2014, its first year of operations, prepared a reconciliation between pretax financial income and taxable income as follows: Pretax financial income $ 800,000 Estimated litigation expense 2,000,000 Installment sales (1,600,000) Taxable income $ 1,200,000 The estimated litigation expense of $2,000,000 will be deductible in 2016 when it is expected to be paid. The gross profit from the installment sales will be realized in the amount of $800,000 in each of the next two years. The estimated liability for litigation is classified as noncurrent and the installment accounts receivable are classified as $800,000 current and $800,000 noncurrent. The income tax rate is 30% for all years. The deferred tax liability—current to be recognized is
Antworten
  • $120,000.
  • $360,000.
  • $240,000.
  • $480,000.
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Chapters 18 & 19 Vocab
Mahogany Alajiah
Coastal Landscapes
Chima Power
River Landscapes
Chima Power
Economic Change
Chima Power
Tectonic landscape
Chima Power
Componentes de la Atmósfera Terrestre Primitiva
Diego Araujo
Resistant Materials Revision Cards
Lukey-Pukey
HUMAN RESOURCES MANAGMENT
geosazatheo4
Biology B2 Flashcards- Cells
Ethan Beadling
Imagen digital
Jessica Pardo