  1. 1The fact that you must pour foundation before you frame the house and that you have to frame the house before you can put on the roof demonstrates scheduling constraints.


    1. AVerdadero
    2. BFalso
  2. 2Too many parallel activities for one individual is an example of a resource constraint.

    1. AVerdadero
    2. BFalso
  3. 3The level of resources each activity will need to be completed in the given amount of time has been estimated; therefore, there are no resource constraints.


    1. AVerdadero
    2. BFalso
  4. 4Resource leveling or smoothing is only used on projects which are resource constrained.


    1. AVerdadero
    2. BFalso
  5. 5Resource bottlenecks are one of the three more common problems encountered in managing multiproject resource schedules.


    1. AVerdadero
    2. BFalso
  6. 6The inability to fit more than two earth movers on a construction site at the same time when more are needed to complete the activity on time is an example of a physical constraint.


    1. AVerdadero
    2. BFalso
  7. 7In a resource-constrained project, the completion date is most likely to change.


    1. AVerdadero
    2. BFalso
  8. 8Having too few programmers and too many engineers is an example of a people resource constraint.

    1. AVerdadero
    2. BFalso
  9. 9If a project needs one earth mover six months from now in order to complete one activity, and the organization has four such machines, there is no equipment resource constraint.


    1. AVerdadero
    2. BFalso
  10. 10A lack of readily available engineers is a technical constraint.


    1. AVerdadero
    2. BFalso

Información

Descripción
Test sobre CH8 T/F, creado por shamuz ALI el 01/04/2019.
Idioma
English
Visitas
0
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?