Pregunta 1

Pregunta
The degree to which a particular stakeholder may be able to positively or negatively affect a Project is his or her:?
Respuesta
  • a. Level of engagement.
  • b. Level of interest.
  • c. Level of commitment.
  • d. Level of influence.

Pregunta 2

Pregunta
A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage the situation?
Respuesta
  • a. Say NO to the stakeholder a few times to dissuade him for submitting more changes.
  • b. Get the stakeholders involved in the project as early as possible.
  • c. Talk to stakeholder´s boss to find ways of directing the stakeholder´s activities to another project.
  • d. Ask that the stakeholder not be included in the stakeholder listing.

Pregunta 3

Pregunta
Stakeholders can be identified in which project management process group?
Respuesta
  • a. Initiating, planning, executing and monitoring and controlling.
  • b. Initiating and planning.
  • c. Planning, and monitoring and controlling.
  • d. Monitoring and controlling, and closing.

Pregunta 4

Pregunta
In considering project stakeholders, the project management team must do all of the following EXCEPT:?
Respuesta
  • a. As much as possible, create conflicts among stakeholders to allow the project team to get its work done.
  • b. Identify the stakeholders.
  • c. Determine stakeholders´ requirements and expectations.
  • d. To the extent possible, manage stakeholders´influence in relation to the requirements to ensure a successful project.

Pregunta 5

Pregunta
In the use of the communications model, all of the following would be considered by the Project Manager except:
Respuesta
  • a. Sender
  • b. Receiver
  • c. Language
  • d. Message

Pregunta 6

Pregunta
All of the following are responsibilities of the project manager EXCEPT:?
Respuesta
  • a. Carefully select the appropriate stakeholders for the project.
  • b. Get stakeholders’ sign-off that the requirements are finalized
  • c. Figure out when stakeholders will be involved in the project and how extensively.
  • d. Ask stakeholders to let you know about problems in project communication and relationships.

Pregunta 7

Pregunta
Project stakeholders should be classified according to their interest, influence, and involvement in the project because:
Respuesta
  • a. Such a classification makes it easier to assign responsibilities to stakeholders.
  • b. Project manager has limited time and it must be used efficiently.
  • c. Stakeholders need to know which group they belong to in terms of interest, influence, and involvement in the project.
  • d. Stakeholders usually have very little time to spend on the project.

Pregunta 8

Pregunta
A project coordinator is distinguished from a project manager in that:?
Respuesta
  • a. A project coordinator has no decision-making power.
  • b. A project coordinator has less decision-making power.
  • c. A project coordinator has no authority to assign work.
  • d. A project coordinator takes on larger projects than a project manager.

Pregunta 9

Pregunta
A stakeholders engagement assessment matrix can be used to identify:?
Respuesta
  • a. Communication gaps.
  • b. Additional stakeholders.
  • c. Key relationships between stakeholders.
  • d. Skill levels of stakeholders.

Pregunta 10

Pregunta
A Project Manager wants to more extensively involve the stakeholders on the Project. Which of the following would be the best way to accomplish this?
Respuesta
  • a. Have a stakeholders periodically review the list of project requirements.
  • b. Invite the stakeholders to attend project status meetings.
  • c. Send status reports to the stakeholders.
  • d. Update the stakeholders on the status of all project changes.
Mostrar resumen completo Ocultar resumen completo

Similar

Francés - Vocabulario Básico
maya velasquez
Los Reyes Católicos y la Organización del Estado
maya velasquez
CÁLCULO MENTAL
JL Cadenas
Vocabulario unidad 13
Laura Maestro
Comentario De Texto 1ºBachillerato
Karo Poghosyan
Los Valores
David Gomez
Elaboración de mapas mentales_1
lariza2893
TEJIDO EPITELIAL
Juan José Fierro
Códigos de la principales aerolíneas
Diego Santos
Límites
Cesar Morgado
Tema 4, Los paisajes de España
Mercedes Graves