PRINCE 2 (Lecture 7)- Directing a Project / Managing Stage Boundaries / Closing a Project

Descripción

Test sobre PRINCE 2 (Lecture 7)- Directing a Project / Managing Stage Boundaries / Closing a Project, creado por Natalie Hallam el 23/02/2015.
Natalie Hallam
Test por Natalie Hallam, actualizado hace más de 1 año
Natalie Hallam
Creado por Natalie Hallam hace más de 10 años
36
2
1 2 3 4 5 (0)

Resumen del Recurso

Pregunta 1

Pregunta
In which process is the initiation of the project authorised?
Respuesta
  • Starting up a Project
  • Initiating a Project
  • Directing a Project
  • Managing a Stage Boundary

Pregunta 2

Pregunta
When does the process of Directing a Projectformally begin?
Respuesta
  • Before Starting up a Project
  • After Starting up a Project
  • After Initiating a Project
  • After Managing a Stage Boundary

Pregunta 3

Pregunta
Which of the following products is NOT reviewed by the Project Board when authorising project closure?
Respuesta
  • Project Initiation Document (PID)
  • Project Brief
  • End Project Report
  • Benefits Review Plan

Pregunta 4

Pregunta
Which role recommends the project closure?
Respuesta
  • The Executive
  • The Senior User
  • The Senior Supplier
  • The Project Manager

Pregunta 5

Pregunta
Which management product is provided to the Project Board with a request to authorise initiation?
Respuesta
  • Project Brief
  • Project Mandate
  • Draft Project Initiation Document
  • Issues Register

Pregunta 6

Pregunta
What is the purpose of an Exception Report?
Respuesta
  • Where there is a forecast to exceed tolerance, it is prepared to inform the Project board of the situation.
  • It provides the Project Board with a summary of stage staus at intervals defined by them.
  • It contains the description, impact assessment and recommendations for a request for change or off-specification.
  • When there is a forecast to exceed tolerance, it replaces the plan which is no longer valid.

Pregunta 7

Pregunta
How often is the Managing Stage Boundary process invoked?
Respuesta
  • At the end of the Starting Up a Project process.
  • At the end of each project.
  • At the end of each stage, except the final one.
  • At the end of each Work Package.

Pregunta 8

Pregunta
Who needs the information gathered in Managing a Stage Boundary to assess the continuing viability of a project?
Respuesta
  • Corporate/Programme Manager
  • Project Board
  • Project Manager
  • Stakeholders

Pregunta 9

Pregunta
Which of the following plans listed below is NOT produced or updated in the Managing a Stage Boundary process?
Respuesta
  • Exception Plan
  • Next Stage Plan
  • Team Plan
  • Project Plan

Pregunta 10

Pregunta
The Project Board may request that the current stage is replanned, and the output from replanning is... which is submitted for Project Board approval?
Respuesta
  • a Stage Plan
  • a Project Plan
  • a Team Plan
  • an Exception Plan

Pregunta 11

Pregunta
What is a purpose of the Closing a Project process?
Respuesta
  • Enable the Project Manager to review whether the project has anything further to contribute.
  • Enable the Project Board to make the decision about whether or not to close the project.
  • Enable the Project Manager to manage the final delivery report.
  • Enable the delivery team to create the specialist products of the final stage.

Pregunta 12

Pregunta
How might the Project Manager use the Project Plan during the Closing a Project process?
Respuesta
  • To update with actuals from the final stage.
  • To update with forecasts for the final stage.
  • To plan the work to review the post-project benefits.
  • To control and monitor the work of the final stage.

Pregunta 13

Pregunta
Which of the following statements represents how the Closing a Project process helps to implement the Risk theme?
Respuesta
  • Describes the activity where the procedure for managing threats for the project is defined.
  • Describes the activity where ongoing opportunities for the project's products are passed on to the operational and maintenance teams.
  • Describes the activity where the delivery team report risks to the Project Manager
  • Describes the activity where risks are captured in the Risk Register.
Mostrar resumen completo Ocultar resumen completo

0 comentarios

There are no comments, be the first and leave one below:

Similar

Cómo Redactar Apuntes de Selectividad
maya velasquez
INGLÉS I GRAMÁTICA BASICA
maya velasquez
Test La Celula
Omar Vazquez Flores
Quiz de articulaciones y múculos
Paola Mendoza
Elaboración de mapas mentales
cielom92
Inglés - Reported Speech
Diego Santos
Deporte para un cerebro más sano
malsoselma
TEST PSICOTÉCNICO Nº 1
Gisel Arreaga
La celula
juan perez
FRACCIONES...
Ulises Yo