  1. 1Project Cost Management- estimation of expected costs for each element and of their distribution over time
    - following control and comparison of costs
  2. 2purpose of costs estimation-obtain approximation of the costs for completion of each project activity and whole project
    - based on available information
    -> subject to iterative (schrittweise Annäherung) adjustments
    - define/check economic needs or project budget
  3. 3cost breakdown- resources typology (men, tools, materials, etc.)
    - direct and indirect costs
    - internal and exteneral costs
    - fixed or variable costs
  4. 4Cost estimation techniques- Analogous estimation
    - Parametric estimation
    -Analytic estimation
  5. 5Analogous estimation- using actual costs of a previous, similar project
  6. 6Parametric estimation- using project characteristics (parameters) in a mathematical model to predict project costs
  7. 7Analytic estimation- estimating cost of individual work items, then summarizing the individual estimates to obtain a project total cost
  8. 8direct costsum of costs of single activities
  9. 9Contingency reserve- cost or time reserve that is used to mange identified risks or "known-unknown"
    - may included in cost estimations
    - estimate reserve based on Expected Monetary Value (EMV)
    - controlled by project manager
  10. 10Management reserve- cost or time reserve that is used to manage the unidentified risk , "unknown-unknown"
    - not an estimated reserve -> random figure
    - not controlled by project manager, only for emergencies
  11. 11Cost estimate- cost of all work packages up to the top level
    -total cost of your project
  12. 12cost baseline= cost estimate + contingency reserve
    -> baseline where you will measure your projects performance
  13. 13Project Budget= Cost Baseline + Management Reserve
  14. 14Budget developing- distribute project budget to appropriate levels of the WBS
    - time-based budget -> performance can be compared
    - Budgeting identifies where and when costs will be expended and establishes means -> performance can be managed
  15. 15Budget at Completion (BAC)- estimated total costs of the project
    - calculated as the sum of direct and indirect costs
  16. 16Project incomes/ project´s plan of revenues- customers payments schedule together with identification of billable events
    - rising curve
  17. 17Funding Limit Reconciliation (Abgleich)- addresses variance between funding limit and planned expenditure -> may require rescheduling of work to level of the rate of expenditure
  18. 18Reduce requirements- task of Project Manager: expand availability and minimize requirements periods
    -> cause delays in the activities that produce costs, but does not affect revenues
  19. 19Project plan development- process of integration of carious aspects of planning ( scope, time, cost, resources, quality, risk , communication )
  20. 20closure of project plan, subject of verification of..- feasibility of the plan from point of view of resources
    - compliance with time objectives
    - compliance with economic objectives
  21. 21Final result of project plan developmentproject baseline (schedule baseline, cost baseline)
    -> represent the accepted and approved plans
  22. 22Schedule compression techniques- used to shorten the scheduled duration without reducing project scope
    -> Fast-tracking: parallelize some activities (increases project risk)
    -> Crashing: compress the duration of some activities ( lowest cost increase)
  23. 23Resource scheduling- Resource allocation over time : evaluation of work loads for each resource over time
    - Comparative analysis of needed and available quantities
    - identification of resources that could become cortical (over-under loads)
    - eliminate possible overloads
  24. 24Resource optimization techniques- Resource Leveling: start and end dates of activities are rescheduled -> change to critical path, increase of project duration
    - Resource Smoothing: activities can be delayed only within their total float -> no change to critical path and project duration
  25. 25Project Plan is a Dossier that should contain- project charter
    - project goals and objective
    - project deliverabkes
    - WBS,OBS,RAM
    - Cost Estimates
    - Baseline (Schedule, Resource, Budget)
    Risk plan, Quality plan, Procurement plan, ..
    --> Project plan is a dynamic document! (= expected to be changed)
  26. 26Baseline-First official version of the project
    - "frozen" -> reference for the control phase of the project (analysis, measuring performance )
    - cannot be modified
  27. 27how to individuate project funding requirements?- comparing cost baseline and management reserves to project income

Información

Descripción
Project Managemnt Fichas sobre Lesson 6, creado por odessa m el 16/10/2019.
Creado por
odessa m
Visitas
2
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?