Case Study Questions

Fred Fulford T10 Commercial Managment of Construction chartership Inglés 11 fichas

Fichas del conjunto (11)

  1. 1How does the JCT contract deal with variations?Section 5 of the contract deal with variations, the definition, and the valuation rules
  2. 2What are the different clauses?5.1 - Definition
    5.2 - Valuation of variations and prove sums
    5.3 - Variation quotation
    5.4 - Contractors right to be present at measurement
    5.5 - Effect to valuation agreement
    5.6 - Measurable work
    5.7 - Daywork
    5.8 - Contractors design portion
    5.9 - Change of conditions of work
    5.10 - Additional provisions
  3. 3What is a cost report?A document used to monitor and present the running cost to the employer
  4. 4what would you included in a cost report?1) Executive summary
    2) Current budget
    3) Contingency position
    4) Commitment & expenditure to date
    5) Anticipated final account
    6) Instructions and variations
    7) Provisional sum agreements
    8) Variation tracker/register
  5. 5How did you manage the risk of variations?Within the cost plan we allowed a percentage contingency that allowed us to mitigate the risk of unknown changes
  6. 6What measures can be taken to control cost during the construction of a project?1) Contingency management
    2) Change control procedures
    3) Managment of provisional sums
    4) Cost reporting
    5) Rolling Final account
    6) Value engineering work shops
  7. 7What ways does the contract administer cost?Different sections 4 & 5 for variations and payments
  8. 8Why might a variation arise?1- Change to spec or drawings
    2- Discrepancy between contract documents
    3- Discrepancy with statutory requirements
    4- Error or ommisions
  9. 9What was your process to negotiating variations?1- Check contract clauses
    2- Analys the contractors variation and tender for duplication
    3- Prepare case for reasons and backup if I don't agree
  10. 10What are the processes of obtaining a cost for a variation?1- Agreement between the employer and contractor
    2- Schedule 2 quotation
    3- QS valuation under valuation rules
  11. 11What does the quotation contain?a) Value of the works
    b) Adjustment for time
    c) Loss and expense claim
    d) Cost for preparing the quote

Información

Descripción
chartership T10 Commercial Managment of Construction Fichas sobre Case Study Questions, creado por Fred Fulford el 14/07/2015.
Creado por
Fred Fulford
Visitas
5
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?