  1. Start

  2. Go into WebEC and master all near-term vessels

  3. Download Availability Report from WebEC

  4. Sort report data

  5. Do all actionable Vessels have terminals assigned?

  6. Determine Voyage, Terminal and Vessel Schedule for unmastered vessels

  7. Master vessels in WebEC and update terminal and ATA information

  8. Assign containers from unmastered Vessels

  9. Update Today's Availability Report

  10. Track container status in terminal sites, verify and update Vessel ETAs

  11. Annotate current container status in the respective column:

    - Customs [C]

    - Vessel Working [V/W]

    - Line [L]

    - Arrived but not Available [(R)]

    - Ready [R]

  12. Update containers in Ready Status (R) to "Available" using WebEC or mass update in WebEZ

  13. Send Availability Report to Distribution List

  14. End

  15. Y

  16. N

Información

Descripción
Diagrama sobre Avail - 2, creado por Rister B el 18/11/2020.
Creado por
Rister B
Visitas
0
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?