Mapa mental

Project Time Management

jonathan villalba huaman Español

Project Time Management

Contenido del mapa

Project Time Management

  1. 1) Plan Schedule Management

    • Definition
      • The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
    • Inputs
      • Project Management Plan
      • Project Charter
      • Enterprise environmental factors
      • Organizational Process Assets
    • Tools and techniques
      • Expert judgement
      • Analytical Technique
      • Meetings
    • Outputs
      • Schedule Management Plan
  2. 2) Define Activities

    • Definition
      • The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
    • Inputs
      • Schedule Management plan
      • Scope Baseline
      • Enterprise environmental factors
      • Organizational Process Assets
    • Tools and techniques
      • Decomposition
      • Rolling wave planning
      • Expert judgement
    • Outputs
      • Activity list
        • Is a comprehensive list that includes all schedule activities required on the project.
      • Activity attributes
      • Milestone list
        • Is a significant point or event in a project.
  3. 3) Sequence Activities

    • Definition
      • The process of identifying and documenting relationships among the project activities.
    • Inputs
      • Schedule Management Plan
      • Activity list
      • Activity attributes
        • May describe a necessary sequence of events or defined predecessor or successor relationships.
      • Milestones list
      • Project scope statement
      • Enterprise environmental factors
      • Organizational Process assets
    • Tools and techniques
      • PDM
      • Dependency demostration
      • Leads and lags
    • Outputs
      • Project schedule network diagrams
      • Project documents updates
  4. 4) Estimate Activity resources

    • Definition
      • The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
    • Inputs
      • Schedule Management Plan
      • Activity list
      • Activity attribute
      • Resource calendars
      • Risk register
      • Activity cost estimates
      • Enterprise environmental factors
    • Tools and techniques
      • Expert judgment
      • Alternatives analysis
      • Published estimating data
      • Bottom-up-estimating
    • Outputs
      • Activity resources requirements
      • Resource breakdown stucture
      • Project documents updates
  5. 5) Estimate Activity durations

    • Definition
      • The process of estimating the number of work periods needed to complete individual activities with estimated resources.
    • Inputs
      • Schedule Management Plan
      • Activity list
      • Activity attributes
      • Resource calendars
      • Activity resource requirements
      • Project scope statement
      • Risk register
      • Resource breakdown structure
      • Enterprise environmental factors
      • Organizational process assets
    • Tools and techniques
      • Expert judgement
      • Analogous estimating
      • Parametric estimating
      • Three point estimating
      • Group decision making techniques
      • Reserve analysis
    • Outputs
      • Activity duration estimates
      • Project documents update
  6. 6) Develop Schedule

    • Definition
      • The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.
    • Inputs
      • Schedule management plan
      • Activity list
      • Activity attributes
      • Project schedule network diagrams
      • Activity resource requirements
      • Resource calendar
      • Activity duration estimates
      • Project scope statement
      • Risk register
      • Project staff assignment
        • Specify which resources are assigned to each activity
      • Resource breakdown structure
      • Enterprise environmental factors
      • Organizational process assets
    • Tools and techniques
      • Schedule network analysis
      • Critical path method
      • Critical chain method
      • Resource optimization techniques
      • Modeling techniques
      • Leads and lags
      • Schedule compression
      • Scheduling tool
    • Outputs
      • Schedule baseline
      • Project schedule
      • Schedule data
      • Project calendars
      • Project management plan updates
      • Project documents updates
  7. 7) Control Schedule

    • Definition
      • The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
    • Inputs
      • Project management plan
      • Project schedule
      • Work performance data
      • Project calendars
      • Schedule data
      • Organizational process assets
    • Tools and techniques
      • Performance reviews
      • Project management software
      • Resource optimization techniques
      • Modeling techniques
      • Leads and lags
      • Schedule compression
      • Scheduling tool
    • Outputs
      • Work performance information
      • Schedule forecasts
      • Change requests
      • Project management plan updates
      • Project documents updates
      • Organizational process assets update

Imágenes y archivos del mapa

  • Project Time Management
  • Project Time Management
  • Project Time Management
  • Project Time Management
  • Project Time Management
  • Project Time Management
  • Project Time Management

Información

Descripción
Mapa Mental sobre Project Time Management, creado por jonathan villalba huaman el 21/04/2018.