SAB2 #31 Perform Integrated Change Control

luisenrique.vega Español

SAB2 #31 Perform Integrated Change Control

Contenido del mapa

SAB2 #31 Perform Integrated Change Control

  • Detailed in pp 154 of RMC
  1. Make only the changes that are right for your project but you need to get your changes approved by the change control board

    • Evaluate the impact (Always first)
    • Identify Options
    • Get the change request approved internally
    • Get customer buy in if required
  2. Project Management plan

  3. Work performance reports

  4. Change requests

  5. Enterprise environmental factors

  6. Meetings

  7. Expert judgment

  8. Change control tools

  9. After Perform Integrated Change Control, we go back to the Direct and Manage Project Work process to put the approved changes in place.

  10. Approved change requests

  11. Project Management plan updates

  12. Change log (All changes, even the ones that don’t get approved, are written in the change log)

  13. Project document updates

Imágenes y archivos del mapa

  • SAB2 #31 Perform Integrated Change Control

Información

Descripción
Mapa Mental sobre SAB2 #31 Perform Integrated Change Control, creado por luisenrique.vega el 02/08/2014.
Visitas
31
Valoración

Más sobre Project Execution, Monitoring and Control

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué deberíamos añadir?