¡GoConqr estrena diseño! Cuéntanos qué te parece.

Mapa mental

Practice Standard for Earned Value Management

camila moreno aldana Ingeniería Español

Contenido del mapa

Practice Standard for Earned Value Management

  1. EVM performance analysis and forecasting

    • Schedule analysis and forecasting
      • schedule variance
        • when is a positive value indicates a favorable condition
        • when is a negative value indicates a unfavorable condition
        • sv=ev-pv
        • this is a percentage sv%= sv=pv
      • schedule performance index
        • indicates how efficiently the project team is using it is time
        • SPI =ev/pv
      • time estimate at completion
        • estimate of when the project will be completed, if current trends continue
        • EAC=(BAC/SPI)/ (BAC/months)
    • cost analysis and forecasting
      • to-complete performance index
        • TCPI=(BAC_EV)/(BAC_AC)
      • cost performance index
        • CPI=EV/AC
          • is the cumulative cost efficiency of a project
      • cost variance
        • CV=EV_AC
          • shows whether a project is under or over budget
      • estimate at completion
        • EAC=AC+ETC
        • ETC=(BAC_EV)/CPI
        • EAC=AC+[(BAC-EV)/CPI]= BAC/CPI
          • equivalent
      • variance at completion
        • VAC=BAC_EAC
        • VAC%= VAC/BAC
      • estimate at completion
        • EAC=BAC/CPI
    • management by exception
      • this practice contributes greatly to the efficiency and effectiveness of project management
  2. Guidance for the use of key EVM practices

    • establish a performance measurement baseline
      • develop time-phased budget for each work task
        • the full scope of work each task or activity must be schedule and resourced
      • assign unambiguous management responsability
        • integrated management of work scope, schedule, and cost requires that a single individual.
      • decompose work scope to a manageable level
        • most work scopes broken down for optimal planning, execution, and control.
      • select earned value measurement techniques for all tasks
        • en EV techniques is selected for each task based on the temporal and physical qualities of the work
      • maintain integrity of performance measurement baseline throughout the project
        • the four key practices established, relating scope, schedule and cost.
    • Measure and Analyze performance against the baseline
      • record resource usage during project execution
        • in EVM, the cost associated with the performance of work scope must be recorded on a regular basis.
      • objectively measure the physical work progress
        • many research projects, however, yield only intangible outcomes until their final product emerges at the end.
      • credit earned value according to earned value techniques
        • also assures thet earned values are credited in the same measurement unit used to establish planned values and record actual cost.
      • analyze and forecast cost/Schedule performance
        • The funtion of EVM forecat is to compare their objetive values with management estimates offered by project delivery team members
      • report performance problems and/or take action
        • it is critical that EVM provide the best possible feedback to those who must make the decisions and take the actions.

Información

Descripción
Ingeniería Mapa Mental sobre Practice Standard for Earned Value Management, creado por camila moreno aldana el 06/11/2017.
Creado por
camila moreno aldana · nov 2017
Actualizado
6 nov 2017
Visitas
0
Historial
  • Creado por camila moreno aldana · 6 nov 2017
  • Copiado por camila moreno aldana · 6 nov 2017
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?