4.1 Develop Project Charter_2

  1. OUTPUTS

    • Project Charter
      • Document issued by the project sponsor that formally authorizes the existence of a project & provides the project manager with the authority to apply organizational resources to the project activities
      • Documents: business needs, assumptions, constraints, high-level requirements, deliverables (products, services or results)
  2. INPUTS

    • Project S.O.W
      • Narrative description of products, services or results to be delivered by a project
      • Internal projects >> project initiator or sponsor provides SOW
      • External Projects >> Customer sends SOW as bid doc
      • SOW References: Business need, project scope description, strategic plan
        • Bus. Need based on: market demand, technology, government regulation, environmental consideration
        • Product Scope: charac of product, service or result
        • Strat Plan: ensures that each project contributes to the overall objective of the organ
    • Business Case
      • Describes the necessary info from a business standpoint to determine whether or not the project is worth the required investment
      • Based on a cost benefit analysis
      • The justification for the project (why we need to do it)
      • Created as the result of: market demand, organizational need, customer request, technological advance, legal requirement, social need
    • Agreements
      • Used to define initial intentions for a project
      • Ex. contracts, memorandums of understanding (MOUs), verbal or written agreements, emails, letter of intent
      • Contracts used when a project is performed for an external customer
    • EEFs
      • enterprise environmental facts that can influence this process
      • Ex. gov regulations, organiz. culture, marketplace condtions
    • OPAs
      • organizational process assets that can influx this process
      • Lessons learnt AND/OR policies & procedures
      • Ex. templates, historical info, lessons learnt knowledge base, policies
  3. T & T

    • Expert Judgement
      • Assess the inputs used to develop the project charter
      • Provide specialized knowledge/training
      • Ex. consultants, industry groups, subject matter experts, PMO, stakeholders
    • Facilitation Techniques
      • Guide the development of the project charter
      • Ex. brainstorming, conflict resolution, problem solving, meeting management
      • Help teams and individuals accomplish project activities

Información

Descripción
Mapa Mental sobre 4.1 Develop Project Charter_2, creado por kerrycampbell el 24/08/2014.
Creado por
kerrycampbell
Visitas
9
Historial
  • Creado por kerrycampbell · 24 ago 2014
  • Copiado por kerrycampbell · 24 ago 2014
Valoración

Más sobre Project Selection and Initiation

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?