Chapter 2: Project evaluation and programme management (3708)

Gideon Van Computer Science Inglés

Chapter 2: Project evaluation and programme management (3708)

Contenido del mapa

Chapter 2: Project evaluation and programme management (3708)

  1. Projects chosen when benefits exceed the costs. Or when part of a strategic objective

    • ICT infrastructure in an organisation can maybe not yield a direct financial benefit but the platform for future projects to do so
    • Portfolio management -> deciding which projects are more likely to give the benefits required
      • Programmes ->Groups of projects which yield common business objectives
  2. 2.2 A business case

    • Also called a feasibility study or Project justification
      • benefits of the project will exceed development, implementation and operational costs
      • Contents of a business case
        • 1. Introduction/ background
          • describes a problem to be solved or an opportunity to be exploited
        • 2. The proposed project
          • a brief outline of the project scope
        • 3. The market
          • The likely demand for the product would need to be assessed
        • 4. Organizational and operational infrastructure
          • How the organization would need to change
        • 5. The benefits
          • These should be express in financial terms where possible
        • 6. Outline implementation plan
          • how the project is going to be implemented. disruptions to the organisation as well
        • 7. Costs
          • the implementation plan will supply information to establish these
        • 8. The financial case
          • combines costs and benefit data to establish value of project
        • 9. Risks
          • business risk
        • 10. Management plan
  3. 2.3 Project portfolio management

    • Decide which projects are to be accepted
    • concerns of project portfolio management include:
      • Evaluating proposals for projects
      • Assessing the risk involved with projects
      • Deciding how to share resources between projects
      • Taking account of dependencies between projects
      • Removing duplication between projects
      • Checking for gaps
    • three elements to PPM
      • portfolio definition
        • Create a central record of all projects within an organization
        • decide whether to have ALL projects in the repository or, say, only ICT projects
        • Note difference between new product development (NPD) projects and renewal projects
          • NPD -> new product developed for customers
          • RP -> Improves the way an oganisation operates
      • portfolio management
        • Actual costing and performance of projects can be recorded and assessed
          • assists with the evaluation of new projects
      • portfolio optimisation
        • balance projects based on risk/reward factor to manage overall risk
    • Issues:
      • Some projects are not worth the man hours to support it and could be better spent on more effective projects
      • below the line projects should maybe not form part of the portfolio definition
      • small projects and support can allow developers to do small rewarding tasks and apply quick fixes
  4. 2.4 Evaluating individual projects

    • Technical assessment
      • Can the functionality be achieved with current affordable technology
      • Organisational policy
      • Cost of technology should be taken into account in the cost-benefit analysis
        • Cost benefit analysis (CBA)
          • Not all projects can be undertaken at one time. The most valuable should be taken on first
          • 1. Identifying all of the costs and benefits of carrying out the projects and operating the delivered application
            • Development costs
            • Set-up costs
            • Operational costs
          • 2. Expressing these costs and benefits in common units
            • Net benefit -> benefits less costs
              • Direct costs such as mentioned in point 1 are east to quantify
    • Cash flow forecasting
      • Important to know when income and expenditure is expected
      • Inflation is not usually taken into account as it proportionately increases expense and income
  5. 2.5 Cost-benefit evaluation techniques

    • Cash flows can be calculated on any period
    • Net profit -> Total income -Total Expense
      • Highest NP is not always the best
    • Payback period
      • This is the time it takes to break even (payback the initial investment) and start generating a surplus of income over outflows
      • Normally a project with the shortest payback period will be chosen as the project is "out of debt" soonest
      • Good tool, not too sensitive to inaccuracies. Does not take into account income and expenditure after the project has broken even
      • Ignores the overall profitability. It doesn't take into account the timing of cashflows
    • Return on investment (ROI)
      • Net profit / total investment
      • Doesn't take account of the timing of cashflows
      • No relation to the interest rates and charges of the banks. Also not the time value of money
    • Discounted Cash Flow Technique (DCF)
      • Net present value (NPV)
        • Accounts for profitability and the timing of cash flows
        • If earning 10% interest p.a then R91 today is equivalent to R100 next year
          • The 10% is the discount rate.
          • Discount rate can be thought of as the target rate of return
          • In the case of 10% rate and one year Discount factor = 1/(1+0.10) = 0.9091 In the case of 10% rate and two years Discount factor = 1/(1.10 x 1.10) =0.8294
        • FV =PV*(1+i)^n
          • PV=FV/(1+i)^n
        • NPV compares different projects but doesn't account for the earnings relative to other investments and the cost of capital
      • Internal Rate of Return (IRR)
        • Compares projects relative to earnings from other investments and the cost of capital
        • A project with IRR of 10% is good if the cost of capital is less than 10% and the capital spent can't earn more than 10% in another investment
        • IRR shows a percentage return so that the percentages can be compared with other investments directly
        • IRR doesn't indicate the absolute size of the return
        • IRR is the percentage discount rate which will produce a zero NPV
        • There may be two discounted rates which will produce a zero NPV. The lowest rate should be chosen
      • NPV and IRR are not a complete answer to economic evaluation
        • Total evaluation must include funding the cash flows. Can I pay the interest payments at the time they needed?
        • Profitability might be high but the risk factors may be too high
        • Consider projects as a part of the whole organisation. Can we fund more projects that are worthy if we do this one?
  6. 2.6 Risk evaluation

    • Risk identification and ranking
      • Identify risks and quantify
      • Risk Matrix -> importance and likelihood of occurring
    • Risk and NPV
      • Riskier project may account for higher discount rates . +5%
    • Cost-benefit analysis
      • Forecast a cash flow for each risk in the risk matrix and the probability of occurring.
      • Sum all the outcomes to get the total expected value
    • Risk Profile analysis
      • More effective when evaluation the profitability of a portfolio of projects
      • By varying some input estimates of a project the sensitivity to changes in those parameters can be tested to identify critical success factors
    • Using decision trees
  7. 2.7 Programme management

    • a group of projects that are managed in a co-ordinated way to gain benefits that would not be possible were the projects to be managed independently’ Ferns
    • Business cycle programmes
      • The projects which are undertaken during a specific planning cycle
    • Strategic programmes
      • Two projects can be run together for a unified outcome. Each is its own project but are run together as a programme
    • infrastructure programmes
      • There may be many systems to maintain as distinct systems part of a single organisation.
    • R&D programmes
      • Future ready systems. Mix between risk and return projects
    • Innovative partnerships
      • Collaborations/Synergies
  8. 2.8 Managing the allocation of resources within programmes

    • When resources are shared between concurrent projects
  9. 2.9 Strategic Programme Management

    • Portfolio of projects contribute to a common objective
    • Based on the OGC -> Office of Government Commerce
  10. 2.10 Creating a programme

Imágenes y archivos del mapa

  • Chapter 2: Project evaluation and programme management (3708)
  • Chapter 2: Project evaluation and programme management (3708)
  • Chapter 2: Project evaluation and programme management (3708)
  • Chapter 2: Project evaluation and programme management (3708)

Información

Descripción
Computer Science Mapa Mental sobre Chapter 2: Project evaluation and programme management (3708), creado por Gideon Van el 20/01/2019.
Creado por
Gideon Van
Visitas
0
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?