¡GoConqr estrena diseño! Cuéntanos qué te parece.

Mapa mental

SAB4#55_Estimate_Activities_Duration

Victor H Cano Español

SAB4#55_Estimate_Activities_Duration

Contenido del mapa

SAB4#55_Estimate_Activities_Duration

  • * Estimate Activity Durations is the process of estimating the numbers of work periods needed to complete individual activities with estimated resources. * Estimate how much time each Activity will take.
  1. Process: Estimate Activity Durations

  2. Process Group: Planning

  3. Knowledge Area: Time Management

  4. 1. Schedule Management Plan

  5. 2. Activity list

  6. 3. Activity attributes

  7. 4. Activity resources requirements

    • Estimate Activities Resources
  8. 5. Resource Calendars

  9. 6. Project Scope Statement

  10. 7. Risk Register

  11. 8. Resource breakdown structure RBS

    • Estimate Activities Resources
  12. 9. EEF

  13. 10. OPAs

  14. 1. Expert Judgment

    • Will come from your project team members who are familiar with the work that has to be done.
  15. 2. Analogous Estimation (Top Down)

    • Is when you look at activities from previous projects that were similar to this one and look at how long it took to do similar work before.
  16. 3. Parametric Estimating

    • Parametric estimating looks at the relationships between variables on an activity to calculate time or cost estimates.  The data can come  from historical records from previous projects, industry requirements, standard metrics, or other sources.
    • Regression Analysis (scatter diagrams)
    • Learning Curve
  17. 4. Three-Point estimating

    • Statistically, there is a very small probability of completing a project on exactly any one date. As we know, things do not always go according to plan. With the three-point technique, estimators give an optimistic (0),  pessimistic (P), and most likely (M)  estimate for each activity.
  18. 5. Group decision-making techniques

    • Involving team members in estimating can be beneficial on many levels. Those doing the work are most likely to have a good understanding of the time required to complete the effort.
  19. 6. Reserve Analysis

    • Means adding extra time to the schedule (called a contingency reserve  or a buffer ) to account for extra risk.
  20. 1.- Activity duration estimates

  21. 2. Project Document Updates

Imágenes y archivos del mapa

  • SAB4#55_Estimate_Activities_Duration

Información

Descripción
Mapa Mental sobre SAB4#55_Estimate_Activities_Duration, creado por Victor H Cano el 14/02/2015.
Creado por
Victor H Cano
Visitas
18
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?