Planning Time

  1. Plan Schedule Management

    • IP:3, I:4, T&T:3
    • M: Includes appropiate control thresholds
    • Inputs
      • PMP (Scope Baseline)
      • Project Charter (Milestones, Approval requirements
      • E/O, Software, procedures, control tools, policies
    • Output: Schedule Management Plan
      • 1. Schedule model development
      • 2. Level of accuracy (range, contingencies)
      • 3. Units of measure (time and resources)
      • 4. Organizational procedures
      • 5. Schedule model maintenance
      • 6. Control thresholds (amount of variation, percentage deviations)
      • 7. Rules of performance measurement (%, EVM, SPI, SU, accounts)
      • 8. Reporting formants and frecuency
  2. Define Activities

    • IP:3, I:4, T&T:3
    • M: Breakdown Work Packages into activities (work effort)
    • Inputs
      • SMP: level of detail
      • Scope Baseline
      • EEF/OPA: PMIS
    • Output: Activity list (description)
    • Output: Activity attributes
      • Duration, resource, cost, responsible
      • LOE: level of effort
      • When completed
      • Predecessor, successor
    • Output:Milestone list (significat point or event)
  3. Sequence Activities

    • IP:4, I:7, T&T:3
    • M: relationships among the activities. Logical sequence of work
    • Inputs
      • SMP: scheduling method
      • Activities, Milestones
      • Project Scope Statement
      • EEF/OPA: tools
    • Output: Project Schedule Network Diagrams, PSND (graphical representation)
    • Output: Project documents updates
      • Activity lists
      • Activity attributes
      • Milestone list
      • Risk register
  4. Estimate Activity Resources

    • IP:7, I:8, T&T:5
    • M:Material, human, equipment, supplies
    • Inputs
      • SMP: level of accuracy and unit of measure
      • Activities
      • Resource calendars (available)
      • EEF/OPA: procedures of rental and purchase
      • Estimate costs
      • Risk register
    • Output: Activity resource requirements (for each work package and period
      • Types and Quantities
      • Basis of estimate
    • Output: Resource Breakdown Structure (RBS) (hierarchical representation by category and type)
    • Output: Project Documents Updates
      • Activity list
      • Activity attributes
      • Resource calendars
  5. Estimate Activity Durations

    • IP:8, I:10, T&T:6
    • M: progressively elaborated
    • Inputs
      • SMP: method, level of accuracy
      • Activities
      • RBS
      • RC
      • PSS
      • RR
      • EEF/OPA: productivity metrics
    • Output: Activity Duration Estimates
      • Number of time periods
      • Not include lags
      • Indication of the range
    • Output: Project documents updates
      • Activity attributes
      • Assumptions
  6. Develop Schedule

    • IP:10, I:13, T&T:8
    • M: dates for completing activities
    • Inputs
      • SMP
      • Define activities (activities)
      • PSND
      • RBS
      • RC
      • Activity durations
      • RR
      • Acquire Project Team (Staff assignments)
      • EEF/OPA
    • O: 1. Schedule Baseline (approved version)
    • O: 2. Project Schedule (presentation)
    • O: 3. Schedule data
    • O: 4. Project calendars (available)
    • O: 5. Project Management Plan Updates
      • Schedule Baseline
      • Schedule Management Plan
    • O: 6. Project documents updates
      • Activity resource requirements
      • Activity attributes
      • Calendars
      • Risk Register

Información

Descripción
Mapa Mental sobre Planning Time, creado por cesarau.garcia.c el 16/03/2015.
Visitas
0
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?