TC#41,42 y 43_DOC, TYPES & LEVELS SCOPE

Is Al Inglés 5,0Valoración media 5,0 de 5 (1 valoración)

Contenido del mapa

TC#41,42 y 43_DOC, TYPES & LEVELS SCOPE

  1. Types of Scope

    • Product Scope
      • The features and functions of the product or service that you and your team are building.
    • Project Scope
      • Is all of the work that needs to be done to make the product.
    • Scope creep
      • Extra Work not controlle
  2. Docs

    • Scope Management Plan
      • Cómo se define, desarrolla, controla y verifica el Alcance?
    • Project Scope Statement
      • Especifica las fronteras del proyecto
  3. WBS LEVELS

    • Activity
      • Actions
      • Inside of Work Package
    • Work Package
      • Last level of WBS
      • Deliverables
      • Group of activities
    • Control Account or Cost Control
      • Group of Workpackages
      • Provide a way to manage and control costs, schedule, and scope at higher level than the work package.
    • Planning package
      • Below the Control Account with known work content but without detailed schedule activities.

Información

Descripción
Mapa Mental sobre TC#41,42 y 43_DOC, TYPES & LEVELS SCOPE, creado por Is Al el 22/01/2016.
Creado por
Is Al
Visitas
12
Valoración
Valoración media 5,0 de 5 (1 valoración)

Más sobre Project Scope and Product Scope

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué deberíamos añadir?