TC_#70_Control Cost

Contenido del mapa
TC_#70_Control Cost
PMBOK
- Knowledge Area: Cost Managemnt
- Process Group: Monitoring & Controling
- Proccess: Control Cost
Progress Reporting
EVM
- Earn Value Measurement
- Measure project performance against the ...
- Scope base line (WORK)
- schedule base line (TIME)
- Cost Base line (COST)
- Can be use to FORECAST of time, cost and work
- TERMS
- PV --> Planned Value
- EV --> Earned Value
- AC --> Actual Cost
- BAC --> Budget At Completion
- EAC --> Estimate At Completion
- ETC --> Estimate To Complete
- VAC --> Variance At Completion
- Formulas
- * --> comulative
- PV ( Plan Value ) = BAC x Planned%Complete
- Variance
- CV (Cost of Variance) = EV -AC
- NEGATIVE --> Over Budget
- POSITIVE --> Under Budget
- SV (Schedule Variance) = EV - PV
- NEGATIVE --> Behind of Schedule
- POSITIVE --> Ahead of Schedule
- VAC ( Variance At Completion ) = BAC - EAC
- CV (Cost of Variance) = EV -AC
- Index
- CPI (Cost Performance Index) = EV/AC
- We are getting $X worth of work of every $1 spend
- GREATER than 1 is good
- LESS than 1 is bad
- SPI (Schedule Performance Index) = EV/PV
- Percent of progress
- GREATER than 1 is good
- LESS than 1 is bad
- CPI (Cost Performance Index) = EV/AC
- Forecast
- EAC (Estimate At Competion)
- AC + Buttom-up ETC
- BAC / CPI*
- Use if BAC have not variance
- You will continue with the same rate of spending
- AC + (BAC -EV)
- used when current variance are thought to be ATIPICAL of the future
- AC +(BAC -EV)/(CPI* x SPI*)
- used when current variance are thought to be TYPICAL of the future
- TCPI (To-Complete Performance Index)
- ( BAC - EV ) / ( BAC - AC )
- GREATER than 1 is BAD
- LESS than 1 is GOOD
- ( BAC - EV ) / ( BAC - AC )
- ETC ( Estimate to Complete )
- EAC - AC = Reestimate
- EAC (Estimate At Competion)
- EV (Earned Value) = BAC x Actual%Complete
- CPI < 1 or SPI < 1 or CV<0 or SV<0 --> TROUBLE
Reserve Analysis
Schedule Base line
Cost Base line
Scope Base line
Data Work Performance
Imágenes y archivos del mapa
Información
- Descripción
- Mapa Mental sobre TC_#70_Control Cost, creado por Paulino Valladar el 07/02/2016.
- Creado por
- Paulino Valladar
- Visitas
- 3
- Valoración