Contract Practice - Interim Valuations & Payment Privisions
Valuations
- Purpose?
- To provide recommendation to certifier on value to them 2 issue thier interim cert.
- the Construction Act Relevant?
- Purpose?
Retention
- JCT Rules
- rtn = certified amount retained by client
- % stated in approx - usually 5%
- Held on wrk executed
- material off site, measured works, listed items, materials on site etc.
- NOT:
- restoration of loss or damage
- statutory fees/ charges
- L&E
- Fluctuations
- cost of emp. MG defects
- opening up 4 inspection
- PC 1/2 is relased
- Emp. gains interest from retention & can keep it
- must be placed into a seperate bank account if specified by MC
- statement of retention must be issued to MC with each interim cert.
- Balance of retention release on issue of certificate of Making Good
- why?
- provide degree of security 4 client
- intended 2 provide funds should issues become apparent e.g. insolvency of MC
- provide incentive to ensure defects are MG
- Weaknesses?
- cost easily be greater than 2.5% or 1.5%
- sets precedence 2 accept defects & snagging
- retention often not treated properly by emp.
- Retention Bonds
- What
- some sectors such as lifts & piling will not accept costs feat. retention but offer bonds in lieu
- form of on demand bond
- inc consideration - in lieu of retention
- remains in force until end of defects period
- provided by bank/ guarantor
- ADVANTAGES:
- assignable
- latham report = retention bonds are a better option than normal retention
- can provide same level of security as interim retention
- does not inflict cashflow problems
- ease MC could b passed onto tender prices
- DISADVANTAGES:
- only advantage over suing if MC goes bust
- not ready access 2 the money as with interim retention
- Types
- its conditional and to enforce you must;
- prove MC default of obs
- prove beneficiary has sustained damages
- prove that damage has been reasonably sustained
- its conditional and to enforce you must;
- Terms of bond
- immediate in insolvency
- payable if MC not performed obligations
- expires after completion of rectification of defects
- What
- JCT Rules
Información
- Descripción
- T017 & T016 Mapa Mental sobre Contract Practice - Interim Valuations & Payment Privisions, creado por alison_patey0437 el 21/04/2013.
- Creado por
- alison_patey0437
- Visitas
- 235
- Etiquetas
- Valoración