Planning introduction and planning techniques

p.christmas-12 Contractors Planning and Estimating Inglés

Contenido del mapa

Planning introduction and planning techniques

  1. Why is planning important

    • Communication
    • Logistics
    • Claims
    • Legally bound
  2. Engineering contract content

    • Within two weeks of contractor submitting the work, a project manager either accepts or gives reasons why they are not
    • Dates when contractor requires important information
    • Float and seperately, time risk allowances
    • Order and timing of operation
    • Dates stated in the contract data or works info
    • Other information required in the works info
    • Health and safety requirements
    • Method statement for each operation which identifies equipment/resources to contractor plans to use
  3. Projects

    • Poor stats
      • 30% of construction is rework
      • 40% of man power on site is wasted
      • at least 10% of materials are wasted
      • 40% of projects are completed late or over budget
    • Main reasons for projects failing
      • Lack of control over progress
      • Insufficient measureables
      • lack of communication with interested parties
      • Lack of quality control
      • Inadequate planning of resources
      • Poor estimation of duration and costs
      • lack of co-ordination of resources and activities
    • Project is a temporary endeviour to create a unique product or service
    • Planning is the process of preparing for the commitment of resources in the most effective fashion
    • Programme is a diagram or list showing the work to be done with assosiated times
    • Programme technique is the method chosen to produce a program
    • planners task is to develop an achievable construction sequence within contractual sequence within contract required timings which fully relates to the contractors available resources
  4. RIBA plan of work

    • Robust protocol which describes the activities involved in a construction project from appraising the clients requirements through to post construction
    • 8 stages
      • 2/ Preperation and brief
      • 3/Concept design
      • 4/ Developed design
      • 5/ Technical design
      • 1/ strategic definition
      • 6/ Construction
      • 7/ Handover and close out
      • 8/ In use
  5. Planning process

    • Consultant
      • Design phases
      • Pre-construction planning (conception to construction)
        • Health and safety planning
          • Check client is aware of duties and a CDM coordinator has been appointed
          • Provide info about remaining risks
          • Provide info for health and safety file
          • eliminate hazards and risks during design
        • Environmental assesment planning
        • Applying for planning permission
        • Quality planning
        • Design planning
      • Construction planning
      • Tender planning
    • Contractors
      • Pre construction planning
      • Conception to construction (pre tender/ contract planning
      • Construction planning (actual site activities)
      • Planning stages
        • Pre-tender planning
        • Pre contract planning
          • Site layout planning
          • Placing orders
          • Requirements schedule
          • Budgetary control proceedure
          • Master programme
          • Organisational structure
          • Pre contract arrangements
  6. Construction programming

    • Programming steps
      • Identify
        • Sequence of tasks/ activities (from drawings)
        • Quantities involved (from B of Q)
        • Construction method (logistics)
        • Risk
        • Choice of construction plant (logistics)
      • Calculate duration of activities
      • Programme/ schedule the tasks/ activities
    • Programme duration
      • Dependant on
        • Resource availability
          • sub contractors
          • plant
          • labour
          • supervision
        • resource output
    • Programming techniques
      • Gantt/ bar chart
      • Network analysis (critical path method) (activity on arrow/ precedence diagrams)
      • Programme evaluation and review technique
      • line of balance
      • time chainage
  7. Network analysis

    • General
      • Method of planning projects by analysisng them into their component activities and depicting these in a network form so as show their detailed relationships throughout the project
      • Network used for optimising the utilisation of resources, progress reporting and control
    • Techniques
      • Activity on arrow
      • Precedence
      • Programme evaluation and review technique (PERT)
    • Logical relationships
      • What activities must be complete before this activity starts??
      • What activities cannot start until this activity is completed??
      • Which activities have no logical relationship with this activity and can take place together??
    • Conventions
      • 1/ Before an activity can begin, all preceeding activities must be completed
      • 2/ Arrows imply logical precedence only. Length and direction are not sagnificant
      • 3/ Events numbers must not be dublicated
      • 4/ Any two events may be directly connected by one activity
      • 5/ Networks can only have one start and one end date
  8. Critical path

    • Shortest logical time to finish the project
    • A continuous chain of events
    • Forward and backward parries produce the earliest times (ET) and latest times (LT) for events
    • Pros
      • Relationship between activities are clear
      • Very detailed for monitoring
    • Cons
      • Technical for client
      • Changes require complete rework

Información

Descripción
(week 2) Contractors Planning and Estimating Mapa Mental sobre Planning introduction and planning techniques, creado por p.christmas-12 el 21/04/2014.
Creado por
p.christmas-12
Visitas
11
Valoración

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?