- 1. Project Plan
- Top level plan
- Project Manager creates during Initiating a Project
- Describes the main products to be delivered and the activities and resources required to deliver
- How project will be split into stages
- At the end of each stage the Project Manager updates the plan - Managing a Stage Boundary
- 2. Stage Plan
- Project Manager creates & provides lower level of detail than the project plan
- Allows Project Manager to track and control work done in the stages
- Project Board reviews each stage plan (Directing a Project) when deciding to authorise the next stage
- 2 processes where Project Manager creates a stage plan:
- Starting up a Project: during Initiation Stage to show work that needs to be done to create the Project Initiation Documentation
- Managing a Stage Boundary: All other stage plans created to show work for each delivery stage and updates during Controlling a Stage
- 3. Team Plan
- Used to forecast and track/control work being completed
- Team Manager creates and updates team plan under Managing Product Delivery
- 4. Exception Plan
- How the project will recover from any breach in tolerances
- Constraints: cost, time, quality, scope
- Tolerance: acceptable level outside of constraints
-
- 1. Design the Plan
- Project Manager decides how to present the plans & estimating techniques
- 2. Define and Analyse Products
- Product based planning techniques used to identify all products that will be delivered
- Project Manager tracks and monitors work completion - main output is Product Descriptions
- Internal Dependencies: when one activity cannot start until another is finished
- External Dependencies: when Project Management Team needs something from outside the project
- 4. Prepare Estimates
- Project Manager forecasts how long tasks will take, how much cost & resources required
- Estimates changes as the project progresses
- 5. Prepare the Schedules
- Forecast dates, Project Manager considers resources & team availability
- 6. Analyse the Risks
- All plans have an element of risk, threats and opportunities are identified and dealt with
- 7. Document the Plan
- All outputs collated into a single plan and contains overall schedule and risks (known)
-
Product Based Planning Techniques
- 1. Write the Project Product Descriptions
- Final outputs of project are documented using Project Product Description by the Project Manager (Starting up a Project)
- 2. Create Product Breakdown Structure
- Graphical tool that helps Project Management Team identify products that will be delivered
- Can be hierarchical, mind map or list
- 3. External Products
- Identify 'external products' such as those that already exist or are being created outside the plan
- 4. Write Product Descriptions
- Product Description of specifications written for every product
- Measurable characteristics - Quality Criteria
- Project Manager creates and is used by Project Board to approve
- 5. Create Product Flow Diagram
- Order in which products will be created
- Project Manager identifies dependencies
Información
- Descripción
- Professional (Prince 2 Study Cards) Prince 2 Diapositivas sobre Chapter 4: Plans Theme, creado por Lynsey Dalgleish el 03/07/2016.
- Creado por
- Lynsey Dalgleish · jul 2016
- Actualizado
- 4 jul 2016
- Visitas
- 9
- Valoración