11. Scope refers to all the work involved in creating the products of the project and the processes used to create them.
- AVerdadero
- BFalso
22. Deliverables are only product-related, such as a piece of hardware or software
- AVerdadero
- BFalso
33. Project scope management includes the processes involved in defining and controlling what is or is not included in a
project- AVerdadero
- BFalso
44. The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.
- AVerdadero
- BFalso
55. The project’s size, complexity, importance, and other factors do not affect how much effort is spent on collecting
requirements for scope planning.- AVerdadero
- BFalso
66. Information from the project charter provides a basis for further defining the project scope.
- AVerdadero
- BFalso
77. Project scope statements must include the project boundaries, constraints, and assumptions.
- AVerdadero
- BFalso
88. The scope of a project is clear and specific from the start.
- AVerdadero
- BFalso
99. Many information technology projects also require detailed functional and design specifications for developing
software, which also should be referenced in the detailed scope statement.- AVerdadero
- BFalso
1010. The project scope statement should reference supporting documents, such as product specifications that will affect
what products are produced or purchased, or corporate policies, which might affect how products or services are
produced.- AVerdadero
- BFalso
1111. The project scope statement, stakeholder requirements documentation, and organizational process assets are the
primary inputs for creating a WBS.- AVerdadero
- BFalso
1212. The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.
- AVerdadero
- BFalso
1313. The WBS is organized solely around project phases.
- AVerdadero
- BFalso
1414. A work package represents one component of the product that the project aims to deliver.
- AVerdadero
- BFalso
1515. A work package must always represent less than 80 hours of work.
- AVerdadero
- BFalso
1616. Given the project management software that is available, it is relatively easy to create a good WBS.
- AVerdadero
- BFalso
1717. The tasks in a WBS must be developed as a sequential list of steps.
- AVerdadero
- BFalso
1818. The executing tasks of the WBS remain constant from project to project.
- AVerdadero
- BFalso
1919. Many organizations provide different guidelines and templates for developing WBSs.
- AVerdadero
- BFalso
2020. Mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.
- AVerdadero
- BFalso
2121. The format of the WBS dictionary is essentially the same for all projects.
- AVerdadero
- BFalso
2222. A unit of work should appear at only one place in the WBS
- AVerdadero
- BFalso
2323. Scope creep if not managed well can lead to the failure of information technology projects.
- AVerdadero
- BFalso
Información
- Descripción
- CIS 4375 Test sobre Chapter 5 T/F, creado por . . el 27/09/2017.
- Autor
- . .
- Idioma
- English
- Visitas
- 9
- Etiquetas
- Valoración
- Aún sin valoraciones Valora este test
Más sobre Project Scope Management