Ayúdanos a dar forma a GoConqr. ¿Qué deberíamos añadir?

Test

Project + Part 1

Nope 200 preguntas

Hacer el test

Preguntas del test (200)

  1. 1A project manager is attempting to establish the proper sequencing and duration of project activities.
    Which of the following would be the MOST beneficial?
    1. ANetwork diagram
    2. BIshikawa diagram
    3. CWBS
    4. DGantt chart
  2. 2Which of the following are characteristics of a project? (Choose two.)
    1. AOngoing
    2. BTemporary
    3. CStart and finish
    4. DAchieving a goal
    5. EConsisting of milestones
    6. FRestricting the budget
  3. 3A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services.

    Which of the following documents will the company MOST likely release FIRST?
    1. ARFO
    2. BRFI
    3. CRFP
    4. DRFQ
  4. 4The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.

    Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
    1. AThe issue log to show why the vendor should be replaced.
    2. BThe team action items to show why the vendor should be replaced.
    3. CThe scope statement to show why the vendor should be replaced.
    4. DA procurement plan to show why the vendor should be replaced.
    5. EA change management plan to have the vendor replaced.
  5. 5A project manager is creating the WBS. In which of the following phases is the project?
    1. AInitiation
    2. BPlanning
    3. CExecution
    4. DClosing
  6. 6Which of the following is a characteristics of a matrix organization?
    1. AAuthority lies solely with the project manager.
    2. BAuthority is directed by the project architect.
    3. CAuthority is shared between the project manager and project coordinator.
    4. DAuthority is shared between functional and project managers.
  7. 7A WBS is being developed for a project.
    Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
    1. AProject team members
    2. BProject sponsor
    3. CProject manager
    4. DProject scheduler
  8. 8A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
    Which of the following documents should the project manager use to obtain this information?
    1. AProject schedule
    2. BBalanced scorecard
    3. CIssue log
    4. DStatus report
  9. 9A stakeholder is unaware of a projects status.
    Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
    1. AStatus report
    2. BOrganizational chart
    3. CRACI matrix
    4. DMeeting minutes
    5. ECommunication plan
  10. 10There are four parallel paths on a network diagram. The summary duration of each path is below:

    A, C, G: 10 weeks -

    A, B, F: 8 weeks -

    D, E, H: 12 weeks -

    D, B, F: 7 weeks -

    Which of the following tasks are on the critical path?
    1. AA, C, G
    2. BA, B, F
    3. CD, E, H
    4. DD, B, F

Información

Descripción
LPI IT Test sobre Project + Part 1, creado por Nope Nope el 21/12/2020.
Idioma
English
Visitas
18
Etiquetas
itlpi
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué deberíamos añadir?