Programme management & strategic change

Description

3.3 outline the characteristics of programme management and its relationship with strategic change
Althea Green
Flashcards by Althea Green, updated more than 1 year ago
Althea Green
Created by Althea Green over 7 years ago
130
1

Resource summary

Question Answer
What is programme management? (part 1) Coordination of multiple projects and change management activities. Interaction with business-as-usual. Transition to BAU must be well organised. Clear visibility of transition issues.
What is programme management? (part 2) Directed by the overall programme objectives. Focused on achievement of strategic objectives. A team containing specialists drawn from the business, i.e. HR team (large projects only).
How are programmes linked to strategic change? Individual projects must be linked to ensure consistency and collective management. Driven by vision set by senior management Flexible and evolutionary as outcomes uncertain and objectives change. Programme deliverables are strategic. Benefits focused.
Show full summary Hide full summary

Similar

10 Study Techniques
PatrickNoonan
Cell Structure
daniel.praecox
C2 - Formulae to learn
Tech Wilkinson
GCSE AQA Physics - Unit 1
James Jolliffe
F211- Module 1 Cells, exchange and transport
eilish.waite
Edexcel Additional Science Chemistry Topics 1+2
El Smith
The Weimar Republic, 1919-1929
shann.w
4 Lesson Planning Tips for Teachers
Micheal Heffernan
1PR101 2.test - Část 4.
Nikola Truong
1PR101 2.test - Část 6.
Nikola Truong
Specific Topic 7.3 Timber selection
T Andrews