SAB8#130 Risk vs Workarounds

Description

Mind Map on SAB8#130 Risk vs Workarounds, created by Alfonso Hernandez on 07/01/2016.
Alfonso Hernandez
Mind Map by Alfonso Hernandez, updated more than 1 year ago
Alfonso Hernandez
Created by Alfonso Hernandez over 8 years ago
18
1

Resource summary

SAB8#130 Risk vs Workarounds
  1. Workaround
    1. A workaround is not a planned response because the problems being addressed were not anticipated ahead of time. Per the name, a “workaround” let’s you “work around” the problem. As soon as it is determined that there is an unanticipated problem, it needs to be addressed, researched and incorporated into the documentation of the project plan
    2. Risk
      1. Contingency plans are developed around those possible issues and they are completed before the threat takes place. These contingency plans should address the objective of the plan, the criteria for activating the contingency plan, the people and responsibilities involved, and the additional details required for implementation.
      Show full summary Hide full summary

      Similar

      Plant Structure and Photosynthesis
      mckenziedev
      STATES OF MATTER
      iamawesomelyepic
      What was the Cold War?
      Emily Tisch
      AQA Sociology AS level
      rhian-hay
      History - Medicine through Time
      Alice Love
      GCSE Science - B1 - You and Your Genes - Genes, Chromosomes and DNA
      GeorgeHaines
      Nazi Germany 1933-39
      c7jeremy
      GCSE REVISION TIMETABLE
      TheJileyProducti
      The Skeletal System - PE GCSE EdExcel
      GeorgeHaines
      FUNCTIONALIST ROLE OF EDUCATION
      ashiana121
      Boston Tea Party
      Shelby Smith