SAB9#70_Control Costs

Description

Mind Map on SAB9#70_Control Costs, created by Salvador Rueda on 25/02/2016.
Salvador Rueda
Mind Map by Salvador Rueda, updated more than 1 year ago
Salvador Rueda
Created by Salvador Rueda over 8 years ago
18
0

Resource summary

SAB9#70_Control Costs

Annotations:

  • In the exam, assume that the project manager is measuring, measuring, measuring on the project 
  1. It is all about knowing how you are doing compared to your plan and making adjustments when necessary
    1. Project funding requirements
      1. Project Management Plan
        1. Work Performance Data
          1. Orginizational Process Assets
            1. Earned value management
              1. Project Management Software
                1. Reserve Analysis
                  1. To-complete performance index (TCPI)
                    1. Performance Reviews
                      1. Earned Value Management
                        1. Integrates COST, TIME and the WORK DONE
                          1. PV - Planned Value
                            1. EV - Erned Value
                              1. AC - Actual Cost (total cost)
                                1. BAC - Budget at Completion
                                  1. EAC - Estimate at Completion
                                    1. ETC - Estimate to Complete
                                      1. VAC - Variance at Completion
                                        1. Formulas
                                          1. CV -Cost Variance EV - AC
                                            1. SV - Schedule Variance EV - PV
                                              1. CPI - Cost Performance Index EV/AC

                                                Annotations:

                                                • The CPI is a cumulative because it is using costs to date. It could be written as CPI(c)=EV(c)/AC(c)
                                                1. SPI - Schedule Performance Index EV/PV
                                                  1. EAC Estimate at Completion
                                                    1. AC + Bottom-up ETC
                                                      1. BAC/CPI
                                                        1. AC+(BAC-EV)
                                                          1. AC+(bac-EV)/CPI(c)XSPI(c))
                                                          2. TCPI - To-Complete Performance Index (BAC-EV)/(BAC-AC)
                                                            1. ETC - Estimate to Complete EAC-AC
                                                              1. VAC - Variance al Complietion BAC-EAC
                                                          3. Forecasting
                                                            1. Work Performance Information
                                                              1. CV - Cost Variance
                                                                1. SV - Schedule Variance
                                                                  1. CPI - Cost Performance Index
                                                                    1. SPI - Schedule Performance Index
                                                                      1. TCPI - To-Complete Performance Index
                                                                        1. EAC - Estimate to Complete
                                                                          1. VAC - Variance al Complietion
                                                                          2. Cost Forecast
                                                                            1. Change request
                                                                              1. Update Management Plan
                                                                                1. Update Project Documents
                                                                                  1. Update OPA´s
                                                                                    1. Progess Reporting
                                                                                      Show full summary Hide full summary

                                                                                      Similar

                                                                                      Mapa Mental - Como Criar um Mapa Mental
                                                                                      miminoma
                                                                                      CHEMISTRY C1 4
                                                                                      x_clairey_x
                                                                                      CHEMISTRY C1 5
                                                                                      x_clairey_x
                                                                                      An Inspector Calls - Themes
                                                                                      Emily Simms
                                                                                      5 Steps to Learning Success
                                                                                      Andrea Leyden
                                                                                      Physical Geography
                                                                                      clongworth25
                                                                                      Variation and evolution Quiz
                                                                                      James Edwards22201
                                                                                      Art styles
                                                                                      Sarah Egan
                                                                                      Using GoConqr to study Economics
                                                                                      Sarah Egan
                                                                                      Get your grammar right!
                                                                                      Sarah Holmes
                                                                                      SalesForce ADM 201 Study Quiz
                                                                                      Brianne Wright