PM Management Processes

Sahara D 26 perguntas

Fazer o quiz

Perguntas do quiz (26)

  1. 1In which project management process group is the detailed project budget created?
    1. AInitiating
    2. BBefore the project management process
    3. CPlanning
    4. DExecuting
  2. 2The project charter is created in which project management process group?
    1. AExecuting
    2. BPlanning
    3. CClosing
    4. DInitiating
  3. 3The project team has just completed the initial project schedule and budget. The next thing to do is to:
    1. AIdentify risks
    2. BBegin iterations
    3. CDetermine communications requirements
    4. DCreate a bar (Grantt) chart
  4. 4A detailed project schedule can be created only after creating the :
    1. AProject budget
    2. BWork breakdown structure
    3. CProject management plan
    4. DDetailed risk assessment
  5. 5The person who should be in control of the project during project planning is the:
    1. AProject manager
    2. BTeam member
    3. CFunctional manager
    4. DSponsor
  6. 6Which of the following is not an input to the initiating process group
    1. ACompany processes
    2. BCompany culture
    3. CHistorical WBs
    4. DProject scope statement
  7. 7The project sponsor has just signed the project charter. What is the next thing to do?
    1. ABegin a complete work packages
    2. BValidate scope
    3. CStart integrated change control
    4. DStart to create management plans
  8. 8The high-level project schedule constraits have just been determined. What project management process group are you in?
    1. AInitiating
    2. BPlanning
    3. CExecuting
    4. DMonitor and Controlling
  9. 9The WBS and WBS dictionary are completed. The project team has begun working on identifying risks. The sponsor contacts the project manager, requesting that the responsability assignment matrix be issued. The project has a budget of US $100,000 and is taking place in three countries using 14 human resources. There is a little risk expected for the project, and teh project manager has managed many projects similar to this one. What is the next thing to do?
    1. AUnderstand the experience of the sponsor on similar projects
    2. BCreate an activity list
    3. CMake sure the project scope is defined
    4. DComplete risk management and issue the responsability assigment matrix
  10. 10A project manager does not have much time to spend on planning before the mandatory start date arrives. He therefore wants to move through planning as effectively as possible. What advice would you offer?
    1. AMake sure you have a signed project charter and then start the WBS
    2. BCreate an activity list before creating a network diagram
    3. CDocument all the known risks before you document the high-level assumptions
    4. DFinalize the quality management plan before you determine quality metrics

Informações

Descrição
Certificado PMP (Dirección de Proyectos) Inglés Quiz sobre PM Management Processes, criado por Sahara D em 12-10-2016.
Idioma
English
Visualizações
254
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?