Prince 2 - Project Management - Processes

clareefairy Prince 2 (Foundation) Inglês 48 flashcards

Flashcards do conjunto (48)

  1. 1What is the first document that starts the entire Project?A Project Mandate
  2. 2What is the 1st action or event in the Processes model?Starting up a Project
  3. 3What are the activities to complete in the 'Starting Up a Project' Process?1. Appoint the Executive & the project Manager.
    2. Capture previous lessons.
    3. Design & appoint the project management team.
    4. Prepare the outline Business Case.
    5. Select the project approach & assemble the project Brief.
    6. Plan the initiation Stage.
  4. 4What are the Products (Documents) or Outputs required from the 'Starting up a Project' Process1st Creation of the following;
    Daily Log
    Lessons Log - Capture Previous Lessons
    (Outline) Business Case
    Project Product Description
    Project Brief
    Stage Plan (Initiation)
  5. 5What action or activity triggers the movement from the 'Starting up a project' to the next Process?Request to initiate a project.
    (Project Manager)
  6. 6What is the 2nd Process called?Directing a Project
  7. 7What is the first activity the Project board complete under the 'Directing a Project' Process?Authorise Initiation
  8. 8What are the documents or Products required for the 'Authorise Initiation' activity to occur?Business Case (Outlined)
    Project approach
    Project Brief
    Plan for Initiation Stage
  9. 9What action or activity triggers the movement from the 'Authorise Initiation' to the next Process?Authority to initiate a project -To Project Manager
    Initiation Notification - To Corporate / Programme Body - This can be the minutes from the meeting.
    (Project Board)
  10. 10What is the name of the 3rd Process?Initiating a Project
  11. 11What are the activities to complete in the 'Initiating a Project' Process?1. Prepare the Risk Management Strategy.
    2. Prepare the Configuration Management Strategy.
    3. Prepare the Quality Management Strategy.
    4. Prepare the Communications Strategy.
    5. Set up the project Controls.
    6. Create the Project Plan.
    7. Refine the business Case.
    8. Assemble the Project Initiation Documentation.
  12. 12What are the documents or Products required for the 'Initiating a Project' activity to occur?1st Creation of the following;
    Risk Management Strategy
    Configuration Management Strategy
    Quality Management Strategy
    Communication Management Strategy
    Project Plan
    Detailed Business Case
    Risk Register
    Configuration Item Records
    Issue Register
    Quality Register
    Benefits Review Plan
    There will also be the:
    PID
    Lesson's Log
  13. 13What action or activity triggers the movement from the 'Initiating a project' to the next Process?Request to deliver a project.
  14. 14What is the 2nd activity the Project board complete under the 'Directing a Project' Process?Authorise the project.
    (This is also where the board send 'Project Authorization notification' to the corporate body.)
  15. 15What are the documents or Products required for the 'Authorise the project ' activity to occur?Risk Management Strategy
    Configuration Management Strategy
    Quality Management Strategy
    Communication Management Strategy
    Project Controls
    Project Plans
  16. 16What is the 3rd activity the Project board complete under the 'Directing a Project' Process?Authorise a Stage or Exception Plan. - This outputs the following activities
    Stage Authorisation
    or
    Exception Plan Approved
  17. 17The 2nd & 3rd activity the Project board complete under the 'Directing a Project' Process often happen at the same time or meeting what are they?Authorise a Project
    Authorise a Stage Plan or Exception Plan
  18. 18What is the 4th action or event in the Processes model?Controlling a Stage
  19. 19What action or activity triggers the movement from the 'Authorise the Project & Authorise a Stage or Exception Plan' to the next Process?Stage Authorisation
    Exception Plan Approved
    (Project board - Project Manager)
  20. 20There are 3 different types of activities under Controlling a stage - what are the activities in the 1st lot of activities?Authorise a work package
    Review Work package status
    Receive completed Work Packages
  21. 21What are the products or documents created in this 1st part of controlling a stage?Created for the 1st time;
    Work Packages
    Highlight Report (Current period)
    Issue Report
    Exception Report
  22. 22There are 3 different types of activities under Controlling a stage - what are the activities in the 2nd area of activities?Review the stage status
    Reports Highlights
  23. 23What are the products or documents created in this 2nd part of controlling a stage?Uupdated:
    Stage Plan (current stage)
    Configur Items Records
    Risk Register
    Issue Register
    Quailty Register
    Work Package
    Lessons Log
    Issue Report
    Daily Log
  24. 24There are 3 different types of activities under Controlling a stage - what are the activities in the 3rd area of activities?Capture & Examine issues and risks
    Escalate issues & Risks
    Take Corrective Action
  25. 25What action or activity triggers the movement from the 'Controlling a Stage' to the next Process, in the start up phase?Authority to Deliver a Work package
  26. 26What is the 5th action or event in the Processes model?Managing Product Delivery
  27. 27What are the required activities in the 'Managing a Product Delivery' Process?Accept a work package
    Execute a work package
    Deliver a work package
  28. 28What are the main products / documents created or maintained in the 'Managing a Product Stage'?Approve - Work Package
    Create - Team Plans & Checkpoint Reviews
    Update - Quality register, Config Item Records, Team Plans, Work packages.
  29. 29What activities or documents help with communication between the 'Managing a Product Delivery' & 'Controlling a Stage' processes?Document - Check Point Reports
    Activites - Completed work package or New Risk (Raise) or New Issue (Raise)
  30. 30When in the 'Controlling a Stage' process how does the project manger keep the project board informed about the project status?Activities - Request for advice or Exception raised.
    Documents - Highlight report, Exception Report, Issue Report
  31. 31What is the 4th activity the Project board complete under the 'Directing a Project' Process?Giving ad hoc direction (The project board may also request for advice to the Corporate body if required). This will then in turn be returned to the project board.
  32. 32During the 'giving ad hoc advice & direction' the project board will completed what activities in relation to controlling a stageProject board advice
    New Issues (raised)
  33. 33What is the 6th action or event in the Processes model?Managing a Stage Boundary
  34. 34What are the activities to complete in the 'Managing a Stage Boundary' Process?Plan the next stage
    Update the Project Plan
    Update the Business Case
    Report Stage End
    Produce an Exception Plan
  35. 35What are the Products (Documents) or Outputs updated for the 'Managing a Stage Boundary' ProcessUpdated:
    PID
    Config Item Record
    Risk Register
    Issue Register
    Quality Register
    Project Plan
    Business Case
    Benefits Review Plan
  36. 36What are the Products (Documents) or Outputs Created for the 'Managing a Stage Boundary' ProcessCreated:
    Stage Plan
    Product Descriptions (Next Stage)
    End Stage Report (Current Stage)
    Lessons Report
    Exception Plan
  37. 37What action or activity triggers the movement from the 'Managing a Stage Boundary' back to the Authorise a Stage or Exception Plan' activity?Request to approve Exception Plan
    or
    Request to approve next Stage Plan
  38. 38What are the Products (Documents) that are required for the following activities Request to approve Exception Plan or Request to approve next Stage PlanPID
    End stage report (current stage)
    Stage Plan (next stage)
    Benefits review plan
    Exception Plan
  39. 39What is the 6th action or event in the Processes model?Closing a Project
  40. 40What is the 5th activity the Project board complete under the 'Directing a Project' Process?Authorise Project Closure
  41. 41What action or activity triggers the movement from the 'Controlling a Stage' to the next Process 'Closing a Project'?Project end approaching
  42. 42What are the activities to complete in the 'Closing a Project' Process?Prepare planned closure
    Prepare premature closure
    Hand over products
    Evaluate the project
    Recommend project closure
  43. 43What are the Products (Documents) or Outputs "Created" for the 'Closing a Project' ProcessCreated
    Follow-on action recommendations
    Lessons Report
  44. 44What are the Products (Documents) or Outputs "UPDATED" for the 'Closing a Project' ProcessUPDATED
    PID
    Project Plan
    Issue Register
    Configure Item Records
    Benefits Review Plan
  45. 45What are the Products (Documents) or Outputs "CLOSED" for the 'Closing a Project' ProcessCLOSED
    Risk Register
    Issue Register
    Quality Register
    Daily Log
    Lessons Log
  46. 46What action or activity triggers the movement from the 'Closing a Project' back to the 'Authorise project closure' activity?Closure Recommendation
  47. 47What are the products (Documents) that need to accompany the Closure recommendation activity?End Project Report
    Benefits Review Plan
    PID
    Business Case
    Lessons report
  48. 48what are the final outputs for the Project board from the 'Authorise Project closure' activityClosure Notification to the Corporate body.
    Approve the following documents;
    End Project report
    (Updated) Business case
    (If updated) Benefits review Plan
    Lesson Log

Informações

Descrição
Prince 2 (Foundation) FlashCards sobre Prince 2 - Project Management - Processes, criado por clareefairy em 03-04-2015.
Criado por
clareefairy
Visualizações
0
Avaliação

Mais sobre PRINCE2 Processes

Fale Conosco

Sobre o que é sua mensagem?

O que a gente deve adicionar?