Prince 2 - Project Management - Processes
Cards in this deck (48)
- 1What is the first document that starts the entire Project?A Project Mandate
- 2What is the 1st action or event in the Processes model?Starting up a Project
- 3What are the activities to complete in the 'Starting Up a Project' Process?1. Appoint the Executive & the project Manager.
2. Capture previous lessons.
3. Design & appoint the project management team.
4. Prepare the outline Business Case.
5. Select the project approach & assemble the project Brief.
6. Plan the initiation Stage. - 4What are the Products (Documents) or Outputs required from the 'Starting up a Project' Process1st Creation of the following;
Daily Log
Lessons Log - Capture Previous Lessons
(Outline) Business Case
Project Product Description
Project Brief
Stage Plan (Initiation) - 5What action or activity triggers the movement from the 'Starting up a project' to the next Process?Request to initiate a project.
(Project Manager) - 6What is the 2nd Process called?Directing a Project
- 7What is the first activity the Project board complete under the 'Directing a Project' Process?Authorise Initiation
- 8What are the documents or Products required for the 'Authorise Initiation' activity to occur?Business Case (Outlined)
Project approach
Project Brief
Plan for Initiation Stage - 9What action or activity triggers the movement from the 'Authorise Initiation' to the next Process?Authority to initiate a project -To Project Manager
Initiation Notification - To Corporate / Programme Body - This can be the minutes from the meeting.
(Project Board) - 10What is the name of the 3rd Process?Initiating a Project
- 11What are the activities to complete in the 'Initiating a Project' Process?1. Prepare the Risk Management Strategy.
2. Prepare the Configuration Management Strategy.
3. Prepare the Quality Management Strategy.
4. Prepare the Communications Strategy.
5. Set up the project Controls.
6. Create the Project Plan.
7. Refine the business Case.
8. Assemble the Project Initiation Documentation. - 12What are the documents or Products required for the 'Initiating a Project' activity to occur?1st Creation of the following;
Risk Management Strategy
Configuration Management Strategy
Quality Management Strategy
Communication Management Strategy
Project Plan
Detailed Business Case
Risk Register
Configuration Item Records
Issue Register
Quality Register
Benefits Review Plan
There will also be the:
PID
Lesson's Log - 13What action or activity triggers the movement from the 'Initiating a project' to the next Process?Request to deliver a project.
- 14What is the 2nd activity the Project board complete under the 'Directing a Project' Process?Authorise the project.
(This is also where the board send 'Project Authorization notification' to the corporate body.) - 15What are the documents or Products required for the 'Authorise the project ' activity to occur?Risk Management Strategy
Configuration Management Strategy
Quality Management Strategy
Communication Management Strategy
Project Controls
Project Plans - 16What is the 3rd activity the Project board complete under the 'Directing a Project' Process?Authorise a Stage or Exception Plan. - This outputs the following activities
Stage Authorisation
or
Exception Plan Approved - 17The 2nd & 3rd activity the Project board complete under the 'Directing a Project' Process often happen at the same time or meeting what are they?Authorise a Project
Authorise a Stage Plan or Exception Plan - 18What is the 4th action or event in the Processes model?Controlling a Stage
- 19What action or activity triggers the movement from the 'Authorise the Project & Authorise a Stage or Exception Plan' to the next Process?Stage Authorisation
Exception Plan Approved
(Project board - Project Manager) - 20There are 3 different types of activities under Controlling a stage - what are the activities in the 1st lot of activities?Authorise a work package
Review Work package status
Receive completed Work Packages - 21What are the products or documents created in this 1st part of controlling a stage?Created for the 1st time;
Work Packages
Highlight Report (Current period)
Issue Report
Exception Report - 22There are 3 different types of activities under Controlling a stage - what are the activities in the 2nd area of activities?Review the stage status
Reports Highlights - 23What are the products or documents created in this 2nd part of controlling a stage?Uupdated:
Stage Plan (current stage)
Configur Items Records
Risk Register
Issue Register
Quailty Register
Work Package
Lessons Log
Issue Report
Daily Log - 24There are 3 different types of activities under Controlling a stage - what are the activities in the 3rd area of activities?Capture & Examine issues and risks
Escalate issues & Risks
Take Corrective Action - 25What action or activity triggers the movement from the 'Controlling a Stage' to the next Process, in the start up phase?Authority to Deliver a Work package
- 26What is the 5th action or event in the Processes model?Managing Product Delivery
- 27What are the required activities in the 'Managing a Product Delivery' Process?Accept a work package
Execute a work package
Deliver a work package - 28What are the main products / documents created or maintained in the 'Managing a Product Stage'?Approve - Work Package
Create - Team Plans & Checkpoint Reviews
Update - Quality register, Config Item Records, Team Plans, Work packages. - 29What activities or documents help with communication between the 'Managing a Product Delivery' & 'Controlling a Stage' processes?Document - Check Point Reports
Activites - Completed work package or New Risk (Raise) or New Issue (Raise) - 30When in the 'Controlling a Stage' process how does the project manger keep the project board informed about the project status?Activities - Request for advice or Exception raised.
Documents - Highlight report, Exception Report, Issue Report - 31What is the 4th activity the Project board complete under the 'Directing a Project' Process?Giving ad hoc direction (The project board may also request for advice to the Corporate body if required). This will then in turn be returned to the project board.
- 32During the 'giving ad hoc advice & direction' the project board will completed what activities in relation to controlling a stageProject board advice
New Issues (raised) - 33What is the 6th action or event in the Processes model?Managing a Stage Boundary
- 34What are the activities to complete in the 'Managing a Stage Boundary' Process?Plan the next stage
Update the Project Plan
Update the Business Case
Report Stage End
Produce an Exception Plan - 35What are the Products (Documents) or Outputs updated for the 'Managing a Stage Boundary' ProcessUpdated:
PID
Config Item Record
Risk Register
Issue Register
Quality Register
Project Plan
Business Case
Benefits Review Plan - 36What are the Products (Documents) or Outputs Created for the 'Managing a Stage Boundary' ProcessCreated:
Stage Plan
Product Descriptions (Next Stage)
End Stage Report (Current Stage)
Lessons Report
Exception Plan - 37What action or activity triggers the movement from the 'Managing a Stage Boundary' back to the Authorise a Stage or Exception Plan' activity?Request to approve Exception Plan
or
Request to approve next Stage Plan - 38What are the Products (Documents) that are required for the following activities Request to approve Exception Plan or Request to approve next Stage PlanPID
End stage report (current stage)
Stage Plan (next stage)
Benefits review plan
Exception Plan - 39What is the 6th action or event in the Processes model?Closing a Project
- 40What is the 5th activity the Project board complete under the 'Directing a Project' Process?Authorise Project Closure
- 41What action or activity triggers the movement from the 'Controlling a Stage' to the next Process 'Closing a Project'?Project end approaching
- 42What are the activities to complete in the 'Closing a Project' Process?Prepare planned closure
Prepare premature closure
Hand over products
Evaluate the project
Recommend project closure - 43What are the Products (Documents) or Outputs "Created" for the 'Closing a Project' ProcessCreated
Follow-on action recommendations
Lessons Report - 44What are the Products (Documents) or Outputs "UPDATED" for the 'Closing a Project' ProcessUPDATED
PID
Project Plan
Issue Register
Configure Item Records
Benefits Review Plan - 45What are the Products (Documents) or Outputs "CLOSED" for the 'Closing a Project' ProcessCLOSED
Risk Register
Issue Register
Quality Register
Daily Log
Lessons Log - 46What action or activity triggers the movement from the 'Closing a Project' back to the 'Authorise project closure' activity?Closure Recommendation
- 47What are the products (Documents) that need to accompany the Closure recommendation activity?End Project Report
Benefits Review Plan
PID
Business Case
Lessons report - 48what are the final outputs for the Project board from the 'Authorise Project closure' activityClosure Notification to the Corporate body.
Approve the following documents;
End Project report
(Updated) Business case
(If updated) Benefits review Plan
Lesson Log
Information