Scrum 116 Qs

Daniel SC Desarrollo profesional Inglês 116 flashcards

Flashcards do conjunto (116)

  1. 1How many categories of roles are defined in Scrum?3
  2. 2Who approves user histories for a SprintScrum Team
  3. 3Which process ensures early delivery of high value?Create Prioritized Product Backlog
  4. 4Flexibility on Scrum projects is achieved through which of the following?Value-based Prioritization.
  5. 5Terson Technologies is working on a month-long software development project for an airline company. Time-boxing is an important Scrum principle. Which of the following pairs has been incorrectly Time-boxed according to general Scrum practice?Sprint Review Meeting: 4 hours
  6. 6Which of the following statements best describes Time-boxing?This principle highlights the focus of Scrum to deliver maximum business value, beginning early in the project and continuing throughout.
  7. 7In a job interview, you are asked to define a distinguishing characteristic of Scrum as compared to various traditional project management methods. Which of the following will be the best answer?Emphasis is on delivering maximum business value in a minimum time span.
  8. 8All of the following are the benefits of collaboration in Scrum projects, EXCEPT:Minimized Change Requests, which reduces rework.
  9. 9Which principle is used to help effectively manage project planning and execution?Value-based Prioritization
  10. 10is created during the Stakeholder meetingProject Vision
  11. 11What is the primary purpose of the Demonstrate and Validate Sprint process?To retrospect the project and identify, document, and internalize the lessons learned.
  12. 12Collaboration is one of the Scrum principles. Which of the following are the three dimensions of this principle?Awareness, Articulation, and Appropriation.
  13. 13Which of the following is NOT a Scrum principle?Refined Reporting.
  14. 14Which of the following processes helps ensure high value deliverables are provided to the customer?Ship Deliverables
  15. 15Which three ideas emphasizes the core philosophy of Scrum?Transparency, inspection, and adaptation
  16. 16In which process is Done Criteria established?Create Prioritized Product Backlog
  17. 17Scrum projects welcome change by using short, iterative ________ that incorporate customer feedback into the deliverables.Sprints
  18. 18Which role in Scrum plays the role of a facilitator and ensures that the Scrum Team is provided with an environment conducive to completing the project successfully?Scrum Master
  19. 19Which of the following best describes the role of a Stakeholder?It is an optional role, which generally consists of a set of documents and/or a group of experts who are typically involved with defining objectives related to quality, government regulations, security, and other key organizational parameters.
  20. 20What is/are developed during User Group meetings?.Epic(s)
  21. 21Which of the following statements best describes Collaboration?This principle focuses on the three core dimensions related to collaborative work: awareness, articulation, and appropriation. It also advocates project management as a shared value-creation process with teams working and interacting together to deliver the greatest value
  22. 22________ is defined as the ability of completed products or deliverables to meet Acceptance Criteria.Quality
  23. 23______________ is responsible for providing guidelines about quality which may be relevant to all Scrum projects in the organization?Scrum Guidance Body
  24. 24Which of the following statements is the best description of the Product Owner role?He/she is the person responsible for achieving maximum business value for the project. He or she is also responsible for articulating customer requirements and maintaining business justification for the project. They represent the Voice of the customer.
  25. 25How many phases are there in Scrum?5
  26. 26Every Scrum cycle begins with a _____________ meeting.Project Vision
  27. 27Which of the following statements best describes Empirical Process Control?This principle focuses on the three core dimensions related to collaborative work: awareness, articulation, and appropriation. It also advocates project management as a shared value-creation process with teams working and interacting together to deliver the greatest value
  28. 28Organization in Scrum is __________Self-organized
  29. 29How many categories of risks are defined in Scrum?5
  30. 30Which principle highlights the focus of Scrum to deliver maximum business value, beginning early in the project and continuing throughout?Value-based Prioritization
  31. 31Which of the following meetings is not usually Time-boxed?Scrum of Scrums
  32. 32Scrum promotes an easy and transparent flow of information throughout the organization. Transparency is depicted through which of the following Scrum practices?Estimate Tasks.
  33. 33Which of the following statements best describes Self-organization?This principle focuses on the three core dimensions related to collaborative work: awareness, articulation, and appropriation. It also advocates project management as a shared value-creation process with teams working and interacting together to deliver the greatest value
  34. 34Flexibility in Scrum is NOT achieved through which of the following?High velocity
  35. 35Which of the following roles is described as a Core role in Scrum?Scrum Master
  36. 36Scrum follows the ________ style of management and is very different from the traditional management of projectsDecentralized
  37. 37Which document is created in the Create Project Vision process?Business case
  38. 38What type of leadership is used in Scrum?Collaborative
  39. 39Which of the following statements on Scrum team is INCORRECT?A Scrum Team should be in place before the project is initiated.
  40. 40As defined in the SBOK, which of the following is a Scrum Aspect?Organization
  41. 41As defined in the SBOK, which of the following is a Scrum Process?Create Deliverables
  42. 42As defined in the SBOK, which of the following a Scrum Principle?Value-based Prioritization
  43. 43Which of the following best defines a project?A collaborative enterprise to either create new products or services or to deliver results as defined in the Project Vision Statement.
  44. 44As defined in the SBOK, which of the following is a phase in Scrum projects?Release
  45. 45Which of the following is NOT an advantage of using Scrum to deliver projects?It ensures that all the benefits are delivered at the end of the project.
  46. 46Which of the following meetings is conducted at the beginning of a Project?Project Vision Meeting
  47. 47Which of the following is an output of the Project Vision˙ Meeting?Project Vision Statement
  48. 48Who among the following creates the Prioritized Product Backlog?Product Owner
  49. 49Which of the following statements on Scrum framework is TRUE?Allows Scrum Teams to take ownership of tasks.
  50. 50Which of the following meetings is conducted at the end of a Sprint to analyze improvement opportunities for the future Sprints?Retrospect Sprint Meeting
  51. 51What is sustainable pace?The pace at which the Scrum Team can work and sustain comfortably for an indefinite period of time.
  52. 52Which of the following is NOT a benefit of using Scrum?Ensures that products are developed over an agreed period of time as it emphasizes detailed planning at the beginning of the project.
  53. 53Which of the following is a benefit of using Scrum?It is based on the principle value-based prioritization thus ensures that highest value is provided in the shortest period possible.
  54. 54Which of the following processes facilitates coordination among Scrum Teams in a Scrum project?Conduct and Coordinate Sprints
  55. 55Scrum framework is best suited for which of the following projects?Projects with changing requirements.
  56. 56Which of the following is NOT an advantage of delivering projects using Scrum?Scrum ensures better coordination among teams through an hierarchical organization structure which delegates authority for all the project aspects from higher level to the lower.
  57. 57Which of the following Scrum principles guides planning in a Scrum project?Value-based prioritization
  58. 58What is self-organization?It refers to emphasizing achieving results by focusing on the needs of the Scrum Team.
  59. 59What is value-based prioritization?It refers to prioritizing creation of high value deliverables over lower value deliverables
  60. 60What is time-boxing?It refers to fixing a certain amount of time for each process and activity in a Scrum project.
  61. 61What is iterative development?It refers to using more than one product development cycle to develop the final project deliverables through the learning from the previous development cycles.
  62. 62What of the following best defines collaboration?It refers to the Scrum Core Team working together and interfacing with the stakeholders to create and validate the deliverables of the project to meet the stated goals.
  63. 63Which of the following is emphasized in Scrum framework?Self-motivation and team responsibility.
  64. 64Which of the following is a style of management used in Scrum framework?Decentralized
  65. 65Time-boxing is not done in which of the following meetings?Retrospect Project Meeting
  66. 66Which of the following statements on Time-boxing is INCORRECT?It ensures that there is detailed upfront planning before every Sprint begins.
  67. 67Which of the following does not aid in ensuring transparency in a Scrum project?Scrum ensures transparency through detailed upfront planning in which all the key stakeholders participate.
  68. 68Which of the following pairs, related to Tuckman?s Model of Group Dynamics, is INCORRECTLY matched?Forming: Team is mature with experience
  69. 69According to SBOK, which of the following is NOT a core dimension of Collaboration?Adaptation
  70. 70Which of the following is NOT an example of the Scrum principle ?Empirical Process Control??Use of fixed amount of time for each process and activity in a Scrum project.
  71. 71All the following statements on Scrum Team are correct, EXCEPT:Prioritizes items in the Prioritized Product Backlog.˙
  72. 72Through which of the following is Inspection in Scrum NOT depicted?Use of information radiators to show the progress of the Scrum Team on completing the tasks in a Sprint.
  73. 73Which of the following statements on colocation is INCORRECT?It enables determination of the order and separation of what must be done now, from what needs to be done later in a Sprint.
  74. 74Which of the following is NOT a principle of Scrum?Stage-by-stage project delivery
  75. 75In Scrum, a short concentrated work cycle is called a/anSprint
  76. 76What are the 6 Scrum principles?Empirical Process Control, Self-organization, Collaboration, Value-based Prioritization, Time-boxing, Iterative Development
  77. 77Scrum follows the ________ style of management and is very different from the traditional management of projectsDecentralized
  78. 78While discussing the concept of Transparency in Empirical Process Control, which of the following is NOT an Artifact?Epic(s).
  79. 79If it were true, which of the following would NOT foster transparency in Scrum projects?Burndown charts can be viewed only by the Scrum Team and the Scrum Master.
  80. 80Which of the following is not a key role in Scrum?Team manager
  81. 81Which of the following is NOT a main idea in Empirical Process Control?Association
  82. 82Every Scrum cycle begins with a _____________ meeting.Project Vision
  83. 83Which of the following is NOT a Scrum principle?Risk-based Prioritization
  84. 84The Product Owner selects team members in collaboration with the˙Scrum Master
  85. 85What is the ideal size of a Scrum team as recommended in the SBOK Guide?6 ? 10 members
  86. 86Quality Assurance in Scrum is _________ centricCustomer
  87. 87Which of the following is NOT an objective of the Retrospect Sprint Meeting?Identify things that the team needs to begin doing.
  88. 88.˙Which of the following roles is described as a Core role in Scrum?Scrum Master
  89. 89Which concept is the basis of the Business Justification aspect in Scrum?Value-driven delivery
  90. 90Which of the following Scrum aspects translate(s) the Scrum principle Value-based Prioritization into practice?A. Business Justification B. Risk C. Change
  91. 91Who can use the SBOK as a reference and knowledge guide?Both experienced Scrum practitioners as well as people with no prior experience or knowledge of Scrum or other project management methods.
  92. 92What is the basis of performance measurement in Scrum?Team performance
  93. 93Which meeting ends a Sprint?Sprint Review Meeting
  94. 94Which of the following is the final step in a Sprint?Prioritized Product Backlog Grooming
  95. 95Collaboration is one of the Scrum principles. Which of the following are the three dimensions of this principle?Awareness, Articulation, and Appropriation.
  96. 96Which of the following roles is described as a non-Core role in Scrum?Chief Scrum Master
  97. 97Which of the following are the core dimensions of collaborative work?Awareness, Articulation, and Appropriation.
  98. 98Who is responsible for coordinating the work of multiple Product Owners?Chief Product Owner
  99. 99How many aspects in Scrum are to be considered for all projects?5
  100. 100The Conduct Daily Standup process is a part of which phase?Implement
  101. 101Which role in Scrum represents the Voice of the Customer?Owner
  102. 102Risks should be identified, assessed, and responded to based on which two factors?Probability and Impact
  103. 103Which principle is used to help effectively manage project planning and execution?Time-Boxing
  104. 104Which process helps in progressive improvement of requirements?Retrospect Sprint
  105. 105When does the Scrum Team discuss progress updates.Groom Prioritized Product Backlog
  106. 106Which role is identified in the Create Project Vision process?Product Owner
  107. 107Which role is primarily responsible for the Business Justification aspect in a Scrum project?Product Owner
  108. 108Which type of management style is followed in Scrum?Autocratic
  109. 109Which principle in Scrum helps to manage changes and build products that satisfy customer needs?Iterative Development
  110. 110Which role in Scrum includes the customers, users, and sponsors, who frequently interact with the Scrum Core Team?Stakeholders
  111. 111Which of the following statements best describes Collaboration?This principle focuses on the three core dimensions related to collaborative work: awareness, articulation, and appropriation. It also advocates project management as a shared value-creation process with teams working and interacting together to deliver the greatest value
  112. 112Which of the following pairs is incorrectly matched?Prioritized delivery: Focus only on business value.
  113. 113A ________ is often used to track the status of the work and activities being carried out by the Scrum Team.Scrumboard
  114. 114Which of the following ensure transparency in Scrum?Scrumboard
  115. 115Which of the following statements on colocation is INCORRECT?It enables determination of the order and separation of what must be done now, from what needs to be done later in a Sprint.
  116. 116Which of the following is NOT a principle of Scrum?Stage-by-stage project delivery

Informações

Descrição
Desarrollo profesional FlashCards sobre Scrum 116 Qs, criado por Daniel SC em 30-06-2022.