Chapter 6: Activity planning (3708)

Gideon Van Computer Science Inglês

Chapter 6: Activity planning (3708)

Conteúdo do mapa

Chapter 6: Activity planning (3708)

  1. Introduction

    • Project plan must include a schedule for start and end times of each activity
      • Ensures resource availability
      • Avoid activities competing for resources
      • indicate which staff does which activity
      • Produce baseline to measure actual against
      • Cash flow forecast
      • Replan project to correct drift from target
    • Activity plan provides a target start and end date for each activity
    • Try have each activity produce a deliverable product or tangible outcome
  2. 6.2 Objectives of activity plan

    • Feasibility assessment
      • Chapter 5 -> is the project possible in time frame and resource constraints
    • Resource allocation
      • Most effective resource allocation to the project
    • Detailed costing
      • How much will project cost and when is the expense incurred
    • Motivation
      • Providing targets. Monitoring actuals against targets
    • Co-ordination SPM (5e)
      • Coordinating different staff to be available for work
    • Completing the project at a minimum time at an acceptable cost
    • Indicate the implications on the time scale by adding constraints -> such as quality requirements
    • Planning continues at each stage from the beginning to product delivery
  3. 6.4 Project schedules

    • Project plan must indicate start and end dates and resources -> It then becomes a project schedule
    • Start with a ideal activity plan -> no constraints on resources
    • Ideal activity plan -> Step 6 identifies the risks of activity
    • Step 7 -> resource allocation -> might affect ideal plan as there is no resource constraints -> ideal plan might need to be adapted to include resource availability
    • Step 8 -> Schedule production -> Start and end dates of activities and resource allocations
  4. 6.5 Projects and activities

    • Defining Project
      • Interrelated activities
      • Starts when at least one activity can begin
      • Complete when all activities complete
      • Activity has start and end and defines a deliverable
      • Activity requires resources
      • Duration of activity must be forecastable
      • Activities may be dependent on one another
    • Identify activities
      • activity based approach
        • Create list of all activities in project
        • Use brainstorming
        • Generate a WBS which identifies the high level tasks
          • Each WBS branch has activities which collectively complete the WBS nodes
          • Advantages -> Likely for tasks catalogue to be complete, and non-overlapping activities
          • Only the leaves are activities
        • Figure 1: A fragment of an activity-based work breakdown structure
      • product based approach
        • Chapter 2
          • Product Breakdown Structure (PBS) and a Product Flow Diagram (PFD)
          • PFD -> Which other products are required as inputs for other product
            • PFD can be transformed to list of activities by determining transformations of one product to the other
          • Advantage - > Less likely a product is omitted from PBS
          • Useful for methodologies -> SSADM and USDP
        • Figure 2: product based approach
      • hybrid approach
        • Hybrid Approach based on deliverables and activities
        • 5 levels of WBS according to IBM
          • Level 1 -> Project
          • Level 2 - > Deliverables such as software, manuals and training course
          • Level 3 -> Components -> key work items needed to produce deliverables
          • Level 4 -> Work packages ->major work items or collections of related tasks
          • Level 5 -> Tasks normally for a single person
  5. 6.6 Sequencing and scheduling activities

    • Sequence activities based on logical relationships
    • Schedule activities -> taking into account resources
  6. 6.7 Network planning models

    • Scheduling technique -> models activities and relationships as a network
    • Network's time flows left to right
    • Best know techniques in this area -> Critical Path Method (CPM) and Program Evaluation Review Technique (PERT)
      • Both use activity on arrow approach to visualise project as network
      • Activities are drawn as arrows
      • Arrows join circles -> circles are start and/or end end of activity or set of activities
    • A variation of technique is -> precedence network
      • Method -> Activity on node networks
      • Activities -> are nodes
      • Links between nodes -> precedence (sequencing)
  7. 6.8 Formulating a network model

    • Network has one start node
    • Network has one end node
    • Each activity has a time
    • Nodes have not execution time
    • Flow from left to right
    • Nodes are numbered
    • Loop free network
    • Dangle free network
    • how to representing lagged activities
      • Staggered activities in parallel
      • Lag is represented on the linking arrow in days -> when it starts and when it ends
    • Hammock activities -> have zero duration
      • Start with first hammocked activity and ends with last
      • Can represent over head costs or resources used at constant over actvities
    • Labeling conventions
  8. 6.9 Adding the time dimension

    • When dependencies are identified and the logical network model is drawn
    • CPM -> concerned with completing the project ASAP and Identifying the activities which will cause a delay (critical path)
    • Each activity requires a duration
    • Forward pass -> calc earliest dates activities can commence and be completed
      • If actual start date known -> can use actual dates, otherwise use days/weeks
      • Activities start at the end of week 0 or begin of week 1 (same thing)
      • Activity A, B and F can start immediately
      • A -> 6 weeks, earliest finish is 6 weeks
      • B -> 4 weeks, earliest 4 weeks, and for F -> 10 weeks
      • C -> earliest start is 6 weeks, earliest finish is week 9
      • E, H and G can start after its longest dependency
    • Backward pass -> calc latest dates activities can start and the critical path
      • We assume that latest completion date is same as earliest completion date
      • Completion for G and H is week 13
      • H -> latest start week 11 (13-2)
      • G -> Latest start week 10 (13-3)
      • C -> Latest completion is start of H
      • E and F -> latest end is week 10
    • Identify the critical path
      • One path of successive activities which define duration of project
      • Activity float (middle number)-> Difference between activity earliest start and latest start or earliest finish and latest finish
      • When the float is zero it is on the critical path
      • Activity span -> maximum allowed time for activity
        • Difference between earliest start and latest end
  9. 6.13 Activity float

    • Measures of activity float
      • Free float -> Activity may be delayed by time frame which doesn't affect other sub activities
        • Difference between earliest completion date and earliest start of subsequent activity
      • Interfering float -> Difference between total float and free float
        • Once free float is used or zero this float tells us how much activity can be delayed without delaying project end date, but delay the start dates of subs
    • Don't issue total float as Activity A using 2 weeks float, leaves activity B with no float. hence critical path time
  10. 6.14 Shorter project duration

    • Add resources, reduce the critical path durations
  11. Activity on Arrow networks

    • Same rules as network nodel
    • Dummy activities
      • When two paths have a common dependency but are in other aspect mutually exclusive
    • Lagged activities
      • Have to use pairs of dummy activities
    • Labelling

Imagens e arquivos do mapa

  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)
  • Chapter 6: Activity planning (3708)

Informações

Descrição
Computer Science Mapa Mental sobre Chapter 6: Activity planning (3708), criado por Gideon Van em 26-03-2019.
Criado por
Gideon Van
Visualizações
4
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?