SAB_#53_Sequence Activities_OK
Schedule Management Plan
- The plan will list any methodologies or tools you planned to use when sequencing.
Activity list
- This includes information about each activity, including known predecessors and successors.
Activity attributes
Milestone list
- Identify the major pieces of work
Project scope statement
- Knowing the full scope of the project help to be sure got all of the activities needed to do the work.
Enterprise environmental factors
- Culture, Government, Standars, Regulation, People, PMIs
Organizational process assets
- Polices, Procedures and Historical Information - Lessons Learn
Precedence Diagramming Method (PDM)
- Diagram the logical relationship between activities
- Network diagrams put your tasks in perspective
- Dependencies (4)
- FS
- FF
- SS
- SF
Dependency determination
- External dependencies
- Sometimes your project will depend on things outside the work you are doing
- Discretionary dependencies
- know that you should set discretionary dependencies based on your knowledge of the best practices for getting the job done.
- Mandatory dependencies
- are the kind that have to exist just because of the nature of the work.
- Internal dependencies
- Some dependencies are completely within the team’s control
- External dependencies
Leads and lags
- Time between Activities
- Lag
- is when you purposefully put a delay between the predecessor task and the successor.
- Lead
- is when you give a successor task some time to get started before the predecessor finishes
- Lag
- Time between Activities
Project schedule network diagrams
- Here’s where you work out how all of the tasks fit together based on their predecessors and determine the critical path through the project.
Project documents updates
- When you’ve sequenced your activities, you might find that some of the documents you’ve created as part of other processes need to be updated.
- Activity attributes updates
- Risk Register Updates
- Activity list updates
Puts everything in order
Involves taking the activities and milestones and sequencing them in the order in which the work will be performed
Informações
- Descrição
- Mapa Mental sobre SAB_#53_Sequence Activities_OK, criado por Gerardo Perez em 27-01-2017.